Post Reply 
 
Thread Rating:
  • 0 Vote(s) - 0 Average
  • 1
  • 2
  • 3
  • 4
  • 5
Islamabad: CDA takes notice of slow pace of work on CitiBank Chowk Flyover
10-21-2008, 10:54 AM
Post: #1
Islamabad: CDA takes notice of slow pace of work on CitiBank Chowk Flyover
CDA takes notice of slow pace

Tuesday, October 21, 2008
by Muhammad Anis

Islamabad

The Capital Development Authority (CDA) has taken notice of slow pace of work on the flyover at Citibank Chowk due to lack of coordination between CDA officials and the Islamabad Traffic Police (ITP).

It has also been learnt that the contractor of the project is facing shortage of material due to restriction on entry of heavy vehicles in the limits of Islamabad Capital Territory (ICT).

CDA Chairman Tariq Mehmood Khan has directed the concerned officials to resolve the issue so that the flyover and roundabout could also be opened for traffic by the extended deadline of January 15, 2009.

The construction of the flyover would require installation of nearly 100 girders each weighing 85,000 kilograms. So far 18 prefabricated girders have been placed on the structure of the flyover.

Out of more than 70 dumpers and trolleys, less than 20 vehicles get permission to reach the site of the project and the rest are stopped at the Golra toll plaza and other entry points to the capital.

The 1,050-metre Citibank Chowk underpass at the Faisal Avenue was opened a day before Eidul Fitr. However the work on lane marking and installation of streetlights is yet to begin.

“I want the momentum be picked up and problems relating to the ITP and security be resolved,” the CDA chairman told officials.

He also said that the clause of penalty should be invoked on the construction firm if it is found responsible for delaying completion of the project.

He said that the pace of work should not be slowed down on any development project. It should rather be expedited.

Tariq Mehmood said that the ongoing work on the construction of e-toll plazas would also be completed in the shortest possible time, as these development projects have become a hurdle in the smooth flow of traffic. These toll plazas are being constructed on Build, Operate and Transfer (BoT) basis at I J Principal Road, Kashmir Highway and Islamabad Highway.

Meanwhile, a steering committee, headed by member estate, has been constituted to look into matters relating to the acquisition of land. The committee members, who also include Director Land Chaudhry Asadullah Faiz, Director Enforcement Faiz Muhammad, would visit problem areas in E-12, I-15 and other ‘stalled sectors’ to prepare a report and give recommendations for immediate action.

http://www.thenews.com.pk/daily_detail.asp?id=142284
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  Deadline Set for the Opening of Shahdara Chowk and Ravi Bridge LRE-Azan 0 621 01-04-2024 01:58 PM
Last Post: LRE-Azan
  LDA DG Takes Charge: Bund Road Projects Undergo Comprehensive Review with Emphasis on LRE-Azan 0 550 12-30-2023 04:47 PM
Last Post: LRE-Azan
  CBD Punjab CEO Imran Amin Leads Final Inspection of Renamed Ghora Chowk Flyover Honor LRE-Azan 0 482 12-22-2023 06:18 PM
Last Post: LRE-Azan
  FBR Takes Strict Measures Against Non-Filers, Issues Warning of Utility Services Disc LRE-Azan 0 489 12-05-2023 07:05 PM
Last Post: LRE-Azan
  Pakistan Railways Takes Action Against Illegal Land Occupation Nationwide LRE-Azan 0 491 11-29-2023 02:43 PM
Last Post: LRE-Azan
  RDA Takes Firm Action Against Promotion of Unlawful Housing Projects LRE-Azan 0 455 11-23-2023 06:15 PM
Last Post: LRE-Azan
  Deadline Set for Completion of Ghora Chowk and Cavalry Ground Projects in Lahore LRE-Azan 0 605 11-18-2023 04:09 PM
Last Post: LRE-Azan
  NHA and CDA Resolve T-Chowk Design Dispute Amicably LRE-Azan 0 533 11-14-2023 02:56 PM
Last Post: LRE-Azan
  RDA Takes Legal Action Against Five Unlawful Housing Societies, Files FIRs LRE-Azan 0 632 10-21-2023 06:54 PM
Last Post: LRE-Azan
  Traffic Plan Amid Cavalry Chowk Underpass Construction Issued LRE-Azan 0 615 09-12-2023 05:47 PM
Last Post: LRE-Azan
  PCBDDA Plans to Open Kalma Chowk Underpass by February 2023 LRE-Azan 0 998 01-25-2023 02:06 PM
Last Post: LRE-Azan
  CDA Serves Notice to Private Housing Scheme LRE-Azan 0 1,226 01-20-2023 02:01 PM
Last Post: LRE-Azan
  Lahore Gulberg to Defence Chowk to be Made 5km Signal Free Corridor LRE-Azan 0 1,470 01-01-2022 06:51 PM
Last Post: LRE-Azan
  Rawal Dam Chowk Interchange likely to be completed by June 2022 LRE-Azan 0 1,746 12-15-2021 05:48 PM
Last Post: LRE-Azan
  RUDN Enclave Islamabad | Public Notice LRE-Azan 0 1,423 11-20-2021 02:59 PM
Last Post: LRE-Azan
  Capital Development authority A Public Notice LRE-Azan 0 1,484 11-18-2021 08:29 PM
Last Post: LRE-Azan
  Islamabad: Work on Bhara Kahu Bypass to Start Next Month LRE-Azan 0 1,295 11-02-2021 06:34 PM
Last Post: LRE-Azan
  Extension work moves at snail’s pace Salman 0 4,501 03-31-2014 07:33 PM
Last Post: Salman
  LDA Notice for Private Housing Schemes in Lahore Division Salman 0 7,089 03-14-2014 05:52 PM
Last Post: Salman
  Flyover on Azadi Chowk : LHC extends stay against demolition Salman 0 4,937 02-26-2014 10:23 PM
Last Post: Salman

Forum Jump:


User(s) browsing this thread: 1 Guest(s)