Muslim town flyover: Deadline looms but only one bridge ready
03-22-2012, 02:58 PM
Post: #1
Muslim town flyover: Deadline looms but only one bridge ready
Muslim town flyover: Deadline looms but only one bridge ready

LAHORE: Chief Minister (CM) Shahbaz Sharif’s deadline of March 22nd for the Communication and Works (C&W) Department to complete the Muslim Town Flyover will not be met. The CM might be able to inaugurate only one bridge of the flyover on March 23rd as work on the second bridge and its additional ramp is still continuing.

Work on the Muslim Town Flyover began on September 20, 2011 and was originally scheduled to be completed on May 30, 2012.

Sharif, however, changed the deadline and told the C&W Department and the National Logistics Cell to complete the flyover by March 20, so he could inaugurate it on March 23rd, on the eve of Pakistan Day (the Kalma Chowk flyover was inaugurated on last independence day).

C&W Department secretary Azam Suleman had told Sharif that the complexity and size of the flyover project made the deadline unrealistic but the CM did not budge from his demand.

“We are trying to open Bridge 1 (heading from Ichhra towards Gaddafi Stadium) for traffic by March 23rd,” said Sabir Khan, the project director. He did not have a completion date for Bridge 2 (from Gadaffi Stadium to Ichhra). “We missed the deadline but are close to completing the work. This project is 2.5 times larger than the Kalma Chowk one,” he said. He added that the CM was satisfied with the speed and quality of work.

The project director said the Muslim Town flyover was also more complex than Kalma Chowk flyover in its design and on account of an additional ramp leading to Wahdat Road (from Bridge 2).

The estimated cost of the project was Rs3.5 billion. Khan said they had not added up the costs as yet but he was sure that work would be completed within the approved budget.

The recommended speed of vehicles on the flyover is 60 km/hour. The total length of the flyover is 2,587 metres (m). Bridge 1 is 963m in length, Bridge 2 is 1,324m long and the ramp leading to Wahdat Road is 301m. Both bridges are three lanes, the Wahdat Road ramp, however, is two-lanes. A seven to 10m special corridor has been left between the flyovers for the upcoming Bus Rapid Transportation System (BRTS).

The number of spans used for the flyovers is 60. The length of the ramp on each side is 145m.

The width of the bridges is 11m each while the Wahdat Road ramp is 8m wide, 244 piles of 1.2m diametre have been used for foundation. There are 57 piers in the entire flyover.

Khan said he was not sure if the CM would inaugurate the flyover on the 23rd
Visit this user's website Find all posts by this user
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  Mareer Chowk Railway Bridge finally becomes operational Salman 0 2,854 01-08-2014 02:43 PM
Last Post: Salman
  Iqbal Town parking plaza ready for businessss Salman 0 4,088 12-16-2013 11:37 AM
Last Post: Salman
  CDA ready to bid for commercial plots Salman 0 4,847 11-18-2013 02:05 PM
Last Post: Salman
  New bridge on Ravi approved Salman 0 6,926 10-30-2013 01:31 PM
Last Post: Salman
  Railway bridge project to be completed by November 30 Salman 0 8,828 10-10-2013 01:22 PM
Last Post: Salman
  CDA extends D12, E12 applications’ deadline by 3 days Salman 0 5,800 10-03-2013 01:18 PM
Last Post: Salman
  Authorities Plan To Build Underpasses And An Overhead Bridge In The DHA Lahore Salman 0 6,352 09-12-2013 08:22 PM
Last Post: Salman
  Mareer Chowk Bridge launching delayed again Salman 0 8,749 08-06-2013 11:08 AM
Last Post: Salman
  Deadline for completion of half part of Mareer Chowk expansion project extended Salman 0 2,554 05-24-2013 01:05 PM
Last Post: Salman
  Work on service roads could not be completed despite passage of deadline Salman 0 2,942 03-12-2013 07:38 PM
Last Post: Salman
  Traders give 3-day deadline to CDA Salman 0 1,949 02-18-2013 06:55 PM
Last Post: Salman
  Residents For Head-Bridge Over Expressway Salman 0 2,621 02-02-2013 01:49 PM
Last Post: Salman
  Jam Sadiq Bridge about to collapse, claims KMC chief Salman 0 3,135 01-15-2013 12:51 PM
Last Post: Salman
  NA body sets Jan 15 as deadline CDA asked to remove Katchi Abadi in I-11 Salman 0 3,157 12-14-2012 12:58 PM
Last Post: Salman
  Work on new Ravi bridge soon: CM Salman 0 4,225 12-12-2012 02:00 PM
Last Post: Salman
  Road expansion project Marrir railway bridge to be dismantled today Salman 0 4,192 11-08-2012 12:10 PM
Last Post: Salman
  December 15 deadline set for completion of development projects in Pindi Salman 0 3,175 11-06-2012 01:34 PM
Last Post: Salman
  Work on Faisal Avenue bridge begin Salman 0 3,727 10-08-2012 12:50 PM
Last Post: Salman
  Fence construction demanded on nullah bridge Salman 0 2,360 10-08-2012 12:29 PM
Last Post: Salman
  Lahore Thokar Niaz Baig bus terminal ready for launch Salman 0 7,046 09-27-2012 02:36 PM
Last Post: Salman

Forum Jump:


User(s) browsing this thread: 1 Guest(s)