Amended design of Mareer Chowk Railway Tunnel still awaits approval
11-30-2012, 02:14 PM
Post: #1
Amended design of Mareer Chowk Railway Tunnel still awaits approval
RAWALPINDI - Snail-paced construction work could delay the completion of the Mareer Chowk Railway Tunnel project, as utility services had not been shifted yet and the amended design of the project had not been approved by Lahore Railway Headquarters.
Sources said that in view of the current pace of work on the project, it would be completed in February 2013. The Railway had completed a diversion line, while other tracks were being removed.
Sources in Rawalpindi Development Authority (RDA) said that the construction work could not be accelerated until 16 feeders of 11KV electricity lines, installed within the wall of the bridge, were not shifted. Maintaining a smooth flow of railway traffic and construction was the other reason behind the delay as there was no alternate passage, the sources added.
When contacted, Railways officials said that they had completed a diversion of tracks, though the final design of the project was waiting approval by the authorities in Railway Headquarters.
Visit this user's website Find all posts by this user
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  Pakistan and China Discuss on Railway Project - Development News LRE-Azan 0 1,468 07-16-2018 07:32 PM
Last Post: LRE-Azan
  Government likely to lay railway line between Islamabad and Muzaffarabad Salman 0 3,372 03-27-2014 07:59 PM
Last Post: Salman
  Approval Given For Razing 12 Slums In The Capital Salman 0 2,724 03-21-2014 04:37 PM
Last Post: Salman
  Flyover on Azadi Chowk : LHC extends stay against demolition Salman 0 2,806 02-26-2014 10:23 PM
Last Post: Salman
  CDA board defers approval of plots restoration policy Salman 0 2,696 02-13-2014 12:23 PM
Last Post: Salman
  PC-1 approval revives hopes for early start of uplift work Salman 0 2,647 02-11-2014 12:25 PM
Last Post: Salman
  Rs. 1.5 billion Allotted For Azadi Chowk Flyover Salman 0 4,007 02-07-2014 07:34 PM
Last Post: Salman
  Work on Azadi Chowk Interchange, New Circular Road Project starts Salman 0 6,348 01-16-2014 01:55 PM
Last Post: Salman
  Mareer Chowk Railway Bridge finally becomes operational Salman 0 3,212 01-08-2014 02:43 PM
Last Post: Salman
  CDA Gives Approval For Bus Service Project Salman 0 2,999 01-02-2014 01:24 PM
Last Post: Salman
  Approval Of Commercial Plans Conditioned With Solar Energy Systems Salman 0 4,415 12-03-2013 04:37 PM
Last Post: Salman
  Delay in approval of building plans by CDA irks investors Salman 0 5,638 11-29-2013 01:17 PM
Last Post: Salman
  RTMA to survey buildings constructed without approval Salman 0 4,880 11-25-2013 01:30 PM
Last Post: Salman
  Rs 1,600m approved for Azadi Chowk shifting Salman 0 7,752 11-18-2013 12:16 PM
Last Post: Salman
  Lowari Tunnel – Construction Work Expected To Complete In Three Years Salman 0 4,283 10-23-2013 12:23 PM
Last Post: Salman
  Railway bridge project to be completed by November 30 Salman 0 9,166 10-10-2013 01:22 PM
Last Post: Salman
  SC takes suo motu notice of Margalla Hills Tunnel Project Salman 0 4,476 09-30-2013 03:44 PM
Last Post: Salman
  Mareer Chowk Bridge launching delayed again Salman 0 9,065 08-06-2013 11:08 AM
Last Post: Salman
  Lahore Ring Ring Development Update : Govt considering change to Southern Loop design Salman 0 12,506 07-05-2013 02:41 PM
Last Post: Salman
  Walled City Of Lahore Authority Asks For The Approval Of Over Rs 2 Billion Projects Salman 0 13,082 07-01-2013 01:31 PM
Last Post: Salman

Forum Jump:


User(s) browsing this thread: 1 Guest(s)