Post Reply 
 
Thread Rating:
  • 0 Vote(s) - 0 Average
  • 1
  • 2
  • 3
  • 4
  • 5
Islamabad: Zero Point Interchange: Work slightly ahead of schedule
06-11-2009, 08:19 AM
Post: #1
Islamabad: Zero Point Interchange: Work slightly ahead of schedule
Mobarik A. Virk
The contractors engaged for the construction of the Zero Point Interchange as well as the Capital Development Authority (CDA) claim that so far the pace of work on the project is being kept according to schedule, in fact slightly ahead of schedule, despite a number of setbacks and hiccups confronted since the project started.

The Project Director, Mumtaz Hussain, told ‘The News’ that 85 per cent of work on structures in ‘Stage-I’ has been completed already while in terms of overall project progress, 47 per cent of work has been completed despite a number of stoppages and halts in work that the project faced right from the start.

This project was launched in September 2008 with a completion time of 24 months at a total cost of Rs2.34 billion. The Project Director told ‘The News’ that they are expecting it to be completed ahead of the schedule date of completion of September 2010.

The project includes four loops, four slip roads in addition to widening of the 1.6 km stretches in all directions on the Kashmir Highway and the Islamabad Highway from the existing Zero Point bridge.

“Right now our two links, one from the Islamabad High to Kashmir Highway leading towards M-2 (Motorway) and the other from the Kashmir Highway to the Islamabad Highway leading towards Faisal Mosque are ready for carpeting. But we are unable to carry out the work because Wapda is yet to start work on re-location of the overhead high tension power lines,” the Mumtaz Hussain told ‘The News’.

“We have already paid the first instalment of Rs40 million to Wapda out of the total of Rs90 million for shifting of these overhead power lines. But the Wapda people have not stirred so far, thus causing a hold-up in work on these two links at present. As soon as they will shift these power lines these two links will be made operative and will ease the pressure of traffic flow,” the project director said.

The other problem, he added, has been the law and order situation, which causes a halt in work from time to time whenever there is a terror strike or a security red alert is announced by the city administration. “The latest example was the three-day interruption of supplies when the city administration banned entry of all trucks and dumpers in the city from June 1 to June 3, 2009. Now all the sand and crush stone is coming from Lawrencepur and Sangjani and because of this ban on entry of trucks and dumpers in the federal capital for these three days our work on the project also suffered as we could not get the required construction material,” Mumtaz Hussain told ‘The News’.

In addition to such bans on entry of trucks and dumpers the work on project site also get affected whenever there is a movement of the VVIPs. “Each time such a step is taken we are compelled to stop all kind of work on the site for at least from two to three hours and at times even more, putting more pressure on us,” he added.

Besides this, he said, the work gets very slow during the morning and afternoon rush hours when people are heading to their work places or returning home at the end of the day because we do not demobilise all the heavy machinery during these hours to avoid any unfortunate incident and facilitate the smooth flow of traffic.

“Delayed rains this year have also caused some problems for us. We continued to receive rains during May and even in the month of June. These months are considered to be ‘dry’ but this year there were quite a few rains during this period. These rains also prevented use of heavy machinery and dampened the pace of work,” he pointed out.

“However,” he added, “despite all these hurdles and hiccups we have managed to keep the pace of work on the project ahead of schedule slightly. Had we not faced these problems we would have been way ahead of the schedule.”

He pointed out that the commuters presently passing through the Islamabad Highway would face some problems after two months (August, 2009) when one side of the Islamabad Highway would be closed for expansion and linking with the loops.

It is believed that the CDA would switch the traffic flow to the ‘Garden Avenue’ at that stage. However, it would be appropriate if the concerned people in the authority may start rehabilitation as well as expansion of the ‘Garden Avenue’, which is a winding two-way narrow road snaking through the Islamabad Park area behind Shakarparian hillock, linking Kashmir Highway/7th Avenue with the Islamabad Highway.

If the CDA may do some good patchwork at a few spots and widen the road by at least employing the ‘Triple Surface Treatment’ (TST) technique on the two-meter shoulders of the Garden Avenue on both sides, it would provide a great relief during that period when the traffic load is expected to be shifted on this link.

http://www.thenews.com.pk/daily_detail.asp?id=182473
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  Commissioner Announces Key Milestones and Schedule for Rawalpindi Ring Road Project LRE-Azan 0 1,185 01-23-2024 03:37 PM
Last Post: LRE-Azan
  Funds Approved for Various Development Projects, Including Link Road Interchange in K LRE-Azan 0 652 01-01-2024 02:03 PM
Last Post: LRE-Azan
  CM Punjab Visits Ring Road Southern Loop-3 Ahead of its Opening LRE-Azan 0 627 10-14-2023 03:24 PM
Last Post: LRE-Azan
  LDA extends tender opening date of Babu Sabu Interchange project LRE-Azan 0 1,008 01-26-2023 03:14 PM
Last Post: LRE-Azan
  Rawal Dam Chowk Interchange likely to be completed by June 2022 LRE-Azan 0 1,767 12-15-2021 05:48 PM
Last Post: LRE-Azan
  Islamabad: Work on Bhara Kahu Bypass to Start Next Month LRE-Azan 0 1,317 11-02-2021 06:34 PM
Last Post: LRE-Azan
  CDA allocates Rs 4.3m for beautifying Zero Point Salman 0 3,947 01-20-2014 07:33 PM
Last Post: Salman
  Work on Azadi Chowk Interchange, New Circular Road Project starts Salman 0 8,676 01-16-2014 01:55 PM
Last Post: Salman
  CDA Yet To Start Construction Of Footpaths Along ZPI (Zero Point Interchange) Salman 0 8,053 10-31-2013 02:29 PM
Last Post: Salman
  CM gives go-ahead to garments city project Salman 0 6,937 10-26-2013 06:14 PM
Last Post: Salman
  Commercialisation fees: DCO seen as going soft on traders ahead of elections Salman 0 4,080 01-29-2013 04:04 PM
Last Post: Salman
  Flawed Interchange design to cost CDA Rs700 million Salman 0 4,469 12-28-2012 03:46 PM
Last Post: Salman
  Go-ahead for Qartaba Chowk flyover Salman 0 5,088 12-08-2012 06:46 PM
Last Post: Salman
  Zero Point to draw closer to airport as work on 3 roads starts today Salman 0 5,199 05-23-2012 11:27 AM
Last Post: Salman
  Financial crunch delays Zero Point loop construction Salman 0 4,492 04-25-2012 12:42 PM
Last Post: Salman
  Pakistan to push ahead with IP gas pipeline project Salman 0 4,067 03-27-2012 12:08 PM
Last Post: Salman
  New toll plaza at Ravi Interchange irks citizens Salman 0 5,672 03-22-2012 02:57 PM
Last Post: Salman
  CDA fails to complete final loop of Zero Point interchange Lahore_Real_Estate 0 4,649 02-20-2012 01:27 PM
Last Post: Lahore_Real_Estate
  Mega development projects to be completed as per schedule Salman 0 4,322 02-02-2012 01:26 PM
Last Post: Salman
  PCAA to complete mega projects on schedule Salman 0 4,081 01-02-2012 12:55 PM
Last Post: Salman

Forum Jump:


User(s) browsing this thread: 1 Guest(s)