Post Reply 
 
Thread Rating:
  • 0 Vote(s) - 0 Average
  • 1
  • 2
  • 3
  • 4
  • 5
26 projects planned to get 37,000MW from River Indus
08-04-2011, 12:52 PM
Post: #1
26 projects planned to get 37,000MW from River Indus
LAHORE (APP) - Water and Power Development Authority (Wapda) has planned 26 projects over River Indus and related tributaries to incorporate their collective 37,000 MW potential into national grid.
The NTDC Deputy Manager (Extra High Voltage), Muhammad Ishaq, stated this, while briefing a media delegation from Lahore at Khan Khuwar Power Station in Besham area of Shangla district.
About the performance of National Transmission and Dispatch Company (NTDC), he said, the Company had the credit of stretching 246 kilometres long 220KV double circuit twin needle transmission line in a very short span of time.
The line, he added, would transmit 325MW generated electricity from power stations installed over Dabair Khuwar (Khuwar, a Pashto word which means tributary or nulla), Khan Khuwar and Allai Khuwar to Islamabad via Mansehra district. Currently, the high tension power line is transmitting 72MW from Khan Khuwar Power Station to the national grid, he maintained.
To a question, Muhammad Ishaq said that after the losses and damages to transmission lines during the historic devastating floods in Pakistan, the General Manager (Grid
System Operation) Sharafat Siyal has been looking after all the 26 power projects over River Indus for which a British company’s was being consulted in technical matters.
Similarly, he said, the SNC Company Canada and NESPAK has completed the feasibility report of 500KV HVDC and HVAC lines for transmission of imported 3400MW coal-based power. While, feasibility report was being prepared for transmission of 2,400MW to be generated through Thar Coal deposits and its PC-I would be forwarded to the government this month.
Established in 1998, the NTDC had been entrusted to embark upon the extension of power transmission lines as well as setting up of new grid stations in the country, he said, asserting, the company’s 8,200 employees are striving day and night to improve and expand the power transmission system.
Now, the NTDC has also connected eight independent power plants of 1,725MW collective capacity in the main power system and these stations included 200MW each of Nishat Power, Nishat Chunia Power and Liberty Powers Faisalabad, and 225MW each of Atlas Power Sheikhupura, Saif Power Sahiwal, Halmor Powers Sheikhupura, Orient Powers Balloki. Similarly, 300MW Chashma
Nuclear Power Plant’s generation has been connected to main power system through 140 kilometre long 220KV transmission line.
To a question, he said, at present there are 12 grid stations of 500KV having capacity of 14850MVA and 26 sub station of 220KV with 15364MVA capacity, and these grids are sufficiently catering to the power needs of the country.
During its three-day tour, the delegation also visited the 220KV Switch Yard at Mangla Power House, 500KV Rawat Grid Station Rawalpindia and Allai Khuwar’s 220KV Stwitch Yard, while, the Project Director (Lahore) Muhammad Amin Khalid, PD (Islamabad) Zaffar Iqbal Niazi, Chief Engineer (GSO) Muhammad
Saleem, Rawalpindi XEn Manzoor Ahmed, Gujranwala XEn Shahid Nazir and Peshawar XEn Arif Khan coordinated effectively the media visit to the transmission lines and grid stations.
Visit this user's website Find all posts by this user
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  DHAI-R Announces 2nd Ballot for Residential Plots in River View South Phase-IV LRE-Azan 0 671 01-12-2024 02:15 PM
Last Post: LRE-Azan
  Ashiana e Quaid Lahore Townhouses and Apartments Planned Salman 0 6,244 04-18-2015 04:56 PM
Last Post: Salman
  Ashiana e Quaid Lahore Townhouses and Apartments Planned Salman 0 5,662 04-14-2015 03:07 PM
Last Post: Salman
  Bahria Town Karachi Plans To Launch Its Master Planned Gated Community Soon Salman 0 5,593 01-09-2014 03:06 PM
Last Post: Salman
  New City River Ravi Lahore : Recruitment of Professionals Salman 0 19,839 11-08-2013 02:29 PM
Last Post: Salman
  Recreational Zones To Be Constructed Around River Ravi Salman 0 10,101 09-17-2013 02:58 PM
Last Post: Salman
  1,000-acre housing project planned Salman 0 4,794 05-15-2013 04:42 PM
Last Post: Salman
  Ill-planned construction continues in Zone-IV despite new regulations Salman 0 5,012 07-16-2012 12:39 PM
Last Post: Salman
  CDA Has Planned To Connect 7th Avenue With BB Road Salman 0 5,031 07-04-2012 02:49 PM
Last Post: Salman
  ‘17 projects underway to generate 20,000MW’ Salman 0 3,989 06-01-2012 12:38 PM
Last Post: Salman
  Bridge over Indus in Rojhan tehsil Salman 0 4,078 05-17-2012 01:28 PM
Last Post: Salman
  4,000MW to be added from Thar coal by 2015: CM Salman 0 4,308 05-09-2012 11:56 AM
Last Post: Salman
  1,000MW wind power projects: Sindh govt assures AEDB of allocating land for projects Salman 0 6,591 04-24-2012 12:14 PM
Last Post: Salman
  Punjab Govt bans new graveyards near river Salman 0 4,298 04-09-2012 12:05 PM
Last Post: Salman
  Indian PM’s offer to supply 5,000MWIndian PM’s offer to supply 5,000MW Salman 0 4,277 03-31-2012 01:45 PM
Last Post: Salman
  ‘Balochistan to import 1,000MW power from Iran’ Salman 0 4,318 03-27-2012 12:13 PM
Last Post: Salman
  Malir River Expressway? In your dreams! Salman 0 4,628 01-19-2012 05:29 PM
Last Post: Salman
  Two of three underpasses within ‘red zone’ planned Salman 0 4,560 01-10-2012 12:38 PM
Last Post: Salman
  Wind power projects: 12 projects of 1,000 MW capacity to be functional in 2013 Salman 0 5,925 12-30-2011 03:37 PM
Last Post: Salman
  City of Late Ravi River Salman 0 4,464 12-04-2011 03:27 PM
Last Post: Salman

Forum Jump:


User(s) browsing this thread: 1 Guest(s)