Paved with gold: Metro bus roadwork to cost thrice as much as Kashmir Highway widenin
03-28-2014, 02:27 PM
Post: #1
Paved with gold: Metro bus roadwork to cost thrice as much as Kashmir Highway widenin
Paved with gold: Metro bus roadwork to cost thrice as much as Kashmir Highway widening

ISLAMABAD:
The material used to construct road infrastructure for metro bus project in Lahore was expensive because of its “high quality” which raised the cost of project, but in the twin cities, it should be kept simple to reduce the cost.
This was one of several decisions made during a meeting held at the Punjab Chief Minister’s Office in Lahore, on January 14 to finalise arrangements about the Rawalpindi-Islamabad metro bus project. The meeting was chaired by Punjab CM Shahbaz Sharif and on January 16, when the minutes of the meeting were issued, this decision was prominently highlighted.
The Islamabad section of the project will be the costliest road project in the history of the federal capital. The total cost of the 13.66-kilometre Islamabad section is Rs23.9 billion. That comes out to Rs1.75 billion per kilometre.
This cost also includes the construction of an interchange at Peshawar Mor and 14 bus stations along the route in Islamabad. The interchange cost mentioned in PC-I of the project is Rs5 billion, the cost of construction of 14 bus stations was Rs770 million, and Rs500 million has been set aside for land acquisition.
If the cost of these three components is excluded, the cost of roadwork alone comes to Rs17.6 billion – almost Rs1.29 billion per kilometre, or Rs1.29 million per metre.

Cost Comparison
There is already a road-widening project underway in the capital for Kashmir Highway. Under this project, a 12-kilometre patch will be widened by building two additional rigid lanes on each sides of the existing road – which required levelling as well — besides resurfacing the existing three lanes on each side, all of which has been budgeted at Rs4.7 billion.
Per kilometre, that works out to cost of this road project is slightly under Rs392 million – barely 30 per cent of the cost of roadwork for the bus project, despite the fact Kashmir Highway will be adding twice as many lanes.
The road infrastructure required for the Islamabad section of the metro bus project also involves a flyover at the intersection of IJP Road, three underpasses at 9th Avenue and an underground at the intersection of 9th Avenue and Jinnah Avenue. Conversely, the Kashmir Highway widening involves the construction and widening of seven bridges over wide streams passing under the road.
The Central Development Working Party, while discussing the original Islamabad Section PC-1 worth Rs24.02 billion, had asked for rationalisation of cost, which came out to Rs23.9 billion.
An official from project consultant Nespak — which worked out the cost — said the figure was calculated on the basis of updated prices notified in the Punjab Government Schedule of Rates.
Meanwhile, a senior CDA Planning official quipped, “It seems that by quoting such high rates for Islamabad metro bus project, the Punjab government wants to justify the cost of Lahore bus project”.
Visit this user's website Find all posts by this user
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  PDWP Approves Three Lahore Development Projects with a Total Cost of PKR 7561.473 Mil LRE-Azan 0 692 01-04-2024 01:56 PM
Last Post: LRE-Azan
  The Dollar Price Increase In The Open Market Also Gold Price Increase Per Tola LRE-Azan 0 1,628 11-27-2021 02:28 PM
Last Post: LRE-Azan
  Rs21.814b signal-free Islamabad Highway corridor Salman 0 4,755 04-09-2015 04:15 PM
Last Post: Salman
  CDA to complete Kashmir Highway project by May 31 Salman 0 4,690 02-25-2014 01:22 PM
Last Post: Salman
  CDA Chairman stresses early completion of Kashmir Highway Salman 0 5,021 02-12-2014 07:48 PM
Last Post: Salman
  CDA chairman inspects work on Kashmir Highway Salman 0 4,769 02-06-2014 12:45 PM
Last Post: Salman
  Prime Minister's low-cost housing scheme: 25 percent share for non-gazetted employees Salman 0 7,385 01-02-2014 01:33 PM
Last Post: Salman
  New CDA Chairman vows to expedite expansion of Kashmir Highway Salman 0 6,005 12-26-2013 05:13 PM
Last Post: Salman
  National Housing Policy 2013 Coming Soon for low-cost houses Salman 0 7,927 11-28-2013 01:31 PM
Last Post: Salman
  Work on Express Highway in Swat to begin shortly Salman 0 6,901 11-25-2013 01:32 PM
Last Post: Salman
  Kashmir Highway project: Instead of receiving funds, CDA conducting inquiry Salman 0 8,421 10-31-2013 11:58 AM
Last Post: Salman
  PM orders strict action against responsible behind Kashmir Highway embezzlement Salman 0 6,015 10-28-2013 03:19 PM
Last Post: Salman
  CDA’s Finance Wing Trammels The Kashmir Highway Construction Project Salman 0 5,334 10-21-2013 06:21 PM
Last Post: Salman
  Linkage of Gwadar Port with Karakorum Highway will multiply Pakistan exports to China Salman 0 8,636 09-24-2013 11:42 AM
Last Post: Salman
  PM Nawaz visits Turkey’s low cost housing scheme Salman 0 9,479 09-19-2013 05:27 PM
Last Post: Salman
  Delay in widening of Kashmir Highway causing traffic jams Salman 0 9,930 08-01-2013 12:45 PM
Last Post: Salman
  Construction Of Kashmir Highway Delayed, Residents Troubled Salman 0 5,212 07-17-2013 12:48 PM
Last Post: Salman
  CDA allocates Rs 334m for Kashmir Highway Salman 0 5,577 07-06-2013 05:18 PM
Last Post: Salman
  CDA directs contractors to speed up extension work of Kashmir highway Salman 0 7,357 05-28-2013 11:33 AM
Last Post: Salman
  CDA for speedy Kashmir Highway expansion Salman 0 4,628 04-15-2013 01:45 PM
Last Post: Salman

Forum Jump:


User(s) browsing this thread: 1 Guest(s)