Post Reply 
 
Thread Rating:
  • 0 Vote(s) - 0 Average
  • 1
  • 2
  • 3
  • 4
  • 5
Rs 1.5 billion project: Parking plaza’s construction delayed for two months
03-29-2009, 06:51 AM
Post: #1
Rs 1.5 billion project: Parking plaza’s construction delayed for two months
* RDA rejects design saying it is not earthquake proof
* NESPAK likely to hand over earthquake proof design to RDA by end of April

By Aamir Yasin
RAWALPINDI: The launch of construction work of Rs 1.5 billion Multi-Tower Parking Plaza at Fowara Chowk, Raja Bazaar, has been delayed for two months as Rawalpindi Development Authority (RDA) has rejected design of the plaza saying it is not earthquake proof.

Earthquake proof design: Sources told Daily Times on Saturday that RDA had assigned NESPAK to design the parking plaza at Suzuki stand, Fowara Chowk, to ease traffic flow in and around Raja Bazaar and adjoining area.

They said NESPAK had completed the design of proposed plaza and handed it over to RDA in January, but RDA rejected the design and asked NESPAK to redesign it.

They said the parking plaza design would be earthquake proof to avoid any untoward situation in the commercial hub of the city. They said NESPAK had completed the land survey of the area and collected soil samples for the earthquake proof design.

They said the firm was likely to hand over the design to RDA by the end of April and the construction work of the project would start by end of May.

They said total area of the plaza would be four kannals and RDA would erect five-storey building, which would have a capacity to accommodate at least 1,000 two and four wheelers on daily basis.

Bus terminal: They said a bus terminal would be established on the ground floor, as after the construction of plaza public transport vans and buses would have no place for stopover.

Talking to Daily Times, RDA Director General Makeen Shahbaz said the civic body had asked NESPAK to redesign the parking plaza.

He said they had completed all their homework to launch the project immediately after receiving the design. He said the area of parking plaza was curved and it required more care in design to make it earthquake proof.

He said RDA had allocated Rs 900 million for the project in the annual development plan and initially they would construct basement and three storeys of the plaza.

The remaining floors would be constructed in next phase in next fiscal year, he said, adding, RDA would construct the plaza with its own resources.

Shahbaz said the civic body was pursuing an international method to ease traffic in the downtown. He said parking plazas were built in all over the developed world.

He said parking plaza was the only solution to the ever-increasing traffic problem in the downtown, as more than 60,000 vehicles ply on roads around the Fowara Chowk. He said they required a parking having a capacity to accommodate 1,200 vehicles. He said the roadside place accommodated only 200 vehicles.

http://www.dailytimes.com.pk/default.asp...009_pg11_1
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  Interest from 21 Construction Firms for Margalla Avenue-M1 Link Project LRE-Azan 0 670 11-01-2023 06:02 PM
Last Post: LRE-Azan
  Chief Secretary Orders Swift Digitization of LDA Records within Two Months LRE-Azan 0 537 10-27-2023 01:55 PM
Last Post: LRE-Azan
  Massive PKR 8 Billion Project Initiated to Tackle Drainage Issues on Lahore's Walton LRE-Azan 0 592 10-02-2023 03:28 PM
Last Post: LRE-Azan
  CDA Approve A Multi-Billion Dollar Project For The Rural Belt LRE-Azan 0 887 03-02-2023 07:27 PM
Last Post: LRE-Azan
  Rawalpindi: Ring Road Project, Rs. 24 Billion Approved in PC-1 LRE-Azan 0 1,483 10-27-2021 01:04 PM
Last Post: LRE-Azan
  CDA won’t tolerate Royal Apartment Plaza encroachments Salman 0 4,897 04-14-2015 03:09 PM
Last Post: Salman
  Inauguration of Metro Bus Service delayed yet again Salman 0 5,147 03-20-2014 06:13 PM
Last Post: Salman
  U-Turns construction project to remain incomplete Salman 0 4,896 01-03-2014 01:15 PM
Last Post: Salman
  Iqbal Town parking plaza ready for businessss Salman 0 6,363 12-16-2013 11:37 AM
Last Post: Salman
  Margalla Avenue Bypass project delayed Salman 0 8,001 12-11-2013 06:10 PM
Last Post: Salman
  LDA to auction 15 shops of Moon Market plaza on 16th Salman 0 5,763 12-09-2013 02:22 PM
Last Post: Salman
  CDA suffers setbacks in parking plazas project Salman 0 6,257 12-04-2013 01:36 PM
Last Post: Salman
  Construction of Iqbal Town parking plaza complete Salman 0 6,793 11-25-2013 01:28 PM
Last Post: Salman
  ‘Illegal’ parking sealed: CDA comes down hard on Centaurus Salman 0 12,702 10-31-2013 02:34 PM
Last Post: Salman
  Modern burn centre to be functional in 2 months Salman 0 6,535 10-28-2013 03:22 PM
Last Post: Salman
  CDA’s Finance Wing Trammels The Kashmir Highway Construction Project Salman 0 5,315 10-21-2013 06:21 PM
Last Post: Salman
  LDA Demolished An Approved Plaza Salman 0 8,427 09-17-2013 02:58 PM
Last Post: Salman
  CDA to auction all parking sites in capital Salman 0 5,392 09-13-2013 01:18 PM
Last Post: Salman
  Mareer Chowk Bridge launching delayed again Salman 0 10,870 08-06-2013 11:08 AM
Last Post: Salman
  Construction Of Kashmir Highway Delayed, Residents Troubled Salman 0 5,194 07-17-2013 12:48 PM
Last Post: Salman

Forum Jump:


User(s) browsing this thread: 1 Guest(s)