Procurement of transformers: HEC accuses Pepco of giving unfair advantage to PEL
05-15-2009, 08:06 AM
Post: #1
Procurement of transformers: HEC accuses Pepco of giving unfair advantage to PEL
MUSHTAQ GHUMMAN
ISLAMABAD (May 15 2009): Heavy Electrical Complex (HEC), a state run entity, on Thursday in a presentation to Minister for Industries and Production Mian Manzoor Wattoo accused the Pakistan Electric Power Company (Pepco) of giving "unfair advantage" to the inexperienced Pakistan Engineering Limited (PEL), in procurement of transformers as the latter did not qualify to participate in tenders.

"The PEL, through cost advantage of using Wapda foundation facilities, quoted unrealistic prices and secured orders of 12 transformers last year. "The PEL cost advantage affecting the HEC was discussed with the Pepco and Mepco, which agreed to load 15-25 per cent to PRL, but the decision has yet not been implemented," the HEC's management stated in the presentation.

Manzoor Wattoo, according to an official statement, who presided over the meeting, assured his full support to the HEC in resolving the issues. Another major demand of the HEC management was immediate delisting of the entity from the privatisation list, ensured regular business from Pepco for optimum capacity utilisation, resolution of other issues like delay in placing of orders, refund of LDCs and warranty claims deductions.

Exemption from submission of bank guarantees on advances/performance and provision of price escalation are some of the demands that were presented by the HEC in the meeting.

"Discos orders are at fixed price and do not incorporate escalation clause, although considerable time is consumed in placement of orders after tender opening. Delay in orders result in abnormal increase in material prices, labour charges and utilities in the intervening period," the HEC said.

According to the presentation, non implementation of 1987 agreement by the Water and Power Development Authority (Wapda), unfair competition by local manufacturers, phasing out of five out of seven types of transformers by Pepco for which technology was originally acquired from China, lack of comprehensive testing facilities and uneconomic power transformers design are the factors negatively effecting the HEC's performance.

In 2006, while realising the financial difficulties, the HEC was exempted from submission of bank guarantee by the Economic Co-ordination Committee (ECC) of the Cabinet, which directed the Wapda to place orders without seeking any guarantee, which was later annulled due to the conditions of the World Trade Organisation (WTO).

Now the unit has again requested the government that Pepco should be advised to exempt it from submission of bank guarantee against advance payment and performance bond, as it is a government concern.

In another presentation, Pakistan Machine Tool Factory (PMTF) asked for provision of funds for rapid indigenisation of wind turbines, and technology transfer agreement with the world's leading technology houses/manufacturers should be signed. The PMTF also proposed that the government should install few wind farms in public sector and award the contract to it. Subsequently, the private investor should also be encouraged to procure locally manufactured equipment.

http://www.brecorder.com/index.php?id=38392
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  Block C of LDA City Jinnah Sector: LDA to start giving possession of plots in first w LRE-Azan 0 564 11-13-2023 06:51 PM
Last Post: LRE-Azan
  NHA giving benefits to blue-eyed contractors, claim senators Salman 0 6,921 11-20-2013 03:20 PM
Last Post: Salman
  Illegal buildings: Civic bodies restrained from giving amenitie Salman 0 4,748 10-10-2012 11:38 AM
Last Post: Salman
  Housing societies not giving plots’ possession Salman 0 5,269 07-10-2012 02:59 PM
Last Post: Salman
  'Chinese entrepreneurs should take advantage of special investment opportunities in P Salman 0 4,944 03-16-2012 02:48 PM
Last Post: Salman
  Sindh govt giving lease to residents of 1,417 goths, katchi abadies, Salman 0 5,342 01-23-2012 01:20 PM
Last Post: Salman
  Loadshedding & PEPCO Financial Crisis: Why? LRE 0 4,498 06-20-2011 08:45 PM
Last Post: LRE
  Nawaz accuses PPP of dillydallying Lahore_Real_Estate 0 3,595 01-29-2011 02:25 PM
Last Post: Lahore_Real_Estate
  ZTBL allocates Rs 60.34b for giving loans to farmers Lahore_Real_Estate 0 4,126 10-14-2010 12:36 PM
Last Post: Lahore_Real_Estate
  WHO approves procurement of pneumonia vaccine Lahore_Real_Estate 0 3,374 09-25-2010 12:10 PM
Last Post: Lahore_Real_Estate
  Procurement of land near Lahore: NICL caused Rs 1.045 billion loss to exchequer: NAB Lahore_Real_Estate 0 4,121 08-30-2010 12:41 PM
Last Post: Lahore_Real_Estate
  Cash-strapped PSO seeks Rs 50 billion from Pepco: receivables stand at Rs 128.6 billi Lahore_Real_Estate 0 4,027 07-13-2010 02:28 PM
Last Post: Lahore_Real_Estate
  Electricity Theft & PEPCO! LRE 0 4,069 06-04-2010 12:39 AM
Last Post: LRE
  LDA mulls giving ownership rights to 'occupants' Lahore_Real_Estate 0 3,543 05-15-2010 11:41 AM
Last Post: Lahore_Real_Estate
  PEPCO Officials Enjoying "NO Load Shedding" LRE 1 5,804 04-28-2010 09:45 AM
Last Post: LRE
  Qureshi accuses India of aiding insurgents LahoreEstate 0 3,351 11-23-2009 04:29 AM
Last Post: LahoreEstate
  Punjab: Law minister accuses Moonis of 'Robert Farm Land' scam Naveed Yaseen 0 3,716 11-07-2009 08:25 AM
Last Post: Naveed Yaseen
  WAPDA and PEPCO Massive irregularities detected in accounts LahoreEstate 0 4,655 10-18-2009 05:12 AM
Last Post: LahoreEstate
  Govt criticized for giving two plots to top bureaucrats as aid begging continues Naveed Yaseen 0 3,354 10-16-2009 07:27 AM
Last Post: Naveed Yaseen
  Rice procurement through PASSCO to cause Rs 12 billion loss to tax-payers Naveed Yaseen 0 3,582 10-13-2009 05:48 AM
Last Post: Naveed Yaseen

Forum Jump:


User(s) browsing this thread: 2 Guest(s)