Road works: Two underpasses put on hold due to lack of funds
11-09-2012, 01:23 PM
Post: #1
Road works: Two underpasses put on hold due to lack of funds
LAHORE:

Plans for the construction of underpasses across the Ring Road in northern Lahore have been shelved for now because of a shortage of funds, The Express Tribune has learnt.

The 9-kilometre Package 3 of the Ring Road’s Northern Loop intersects three major roads and the government had planned to build underpasses at each intersection. One underpass at Shadbagh has been built; the other two were planned on the road going from Bhogewal to Karol Ghati, and on Bheni Road at Mehmood Booti.

A Lahore Ring Road Authority (LRRA) official said that construction had been put on hold subject to the availability of the required funding.

The government is currently engaged with the construction of the Metro Bus Service and the expansion of Multan Road, two major projects worth billions of rupees. Plans to expand Ravi Bridge were also shelved earlier due to a lack of funds. And the government recently invited private companies to build the Southern Loop of the Ring Road as part of a public-private partnership because it does not have the funds to build the 48-km road on its own.

LRRA Deputy Director Najam Waheed said that if a road is intersected by a highway or motorway, the government should provide road users an alternative in the form of a flyover or underpass. Presently, he said, additional turns had been created on Package 3 to accommodate local residents who need to cross the road. “These u-turns are problematic as they slow traffic on the Ring Road,” he said. They were not particularly convenient for vehicles travelling locally either, he said, as they still needed to make a detour of several kilometres.

LRRA Chief Engineer Javed Ilyas said that the underpasses had been put on hold owing to the non-availability of funds. He said the project would be started “as soon as the government has some funds”.

High enough?

The underpass at Shadbagh was built in 2009 and quickly came under criticism because, at 3.6 metres, it is not high enough for heavy traffic. The northern parts of Lahore are home to several small industries and warehouses and a National Engineering Services of Pakistan study showed that the three roads bisected by the Ring Road are commonly used by heavy traffic.

Keeping the criticism in view, Project Management Unit officials proposed to the Planning and Development Department that the next two underpasses be 5.1 metres tall so they can accommodate large vehicles, said an official familiar with the project. However, the department turned down the proposal because at Rs1.35 billion, the project was too expensive. “We were advised to revise the project to lower cost,” he said,

The official said that a second proposal was sent to the Planning and Development Department for two flyovers costing Rs1.21 billion. This proposal was also turned down for being too expensive.

Finally, it was proposed that two 3.6-metre underpasses be built at the intersections at a cost of Rs1.04 billion. The project was approved last month and forwarded to the Chief Minister’s Secretariat. There, it was put on hold due to a lack of funds, said the official.

Khalid Javed of the Planning and Development Department section concerned said that the NESPAK study of the roads did show that they were used by heavy traffic, but the numbers were not so high as to merit building the more expensive underpasses.

He said that the shorter underpasses would still provide relief to locals and allow the closing of the additional u-turns on the Ring Road. He said that it wasn’t unreasonable to expect trucks to add a few extra kilometres to their journeys via the Ring Road. He said he was unaware of any postponement of the project.
Visit this user's website Find all posts by this user
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  Funds Approved for Various Development Projects, Including Link Road Interchange in K LRE-Azan 0 651 01-01-2024 02:03 PM
Last Post: LRE-Azan
  SBP & CDC Launched RAAST Payments Facility For Mutual Funds LRE-Azan 0 584 11-02-2023 06:37 PM
Last Post: LRE-Azan
  RAAST Online Funds Transfer Service to be Unavailable on Sunday LRE-Azan 0 681 09-02-2023 02:48 PM
Last Post: LRE-Azan
  LWMC has Launched an Operation to make Mall Road a Model road of the City LRE-Azan 0 4,501 08-09-2018 06:35 PM
Last Post: LRE-Azan
  Khaira Distributory Road that links Package 17 of Ring Road to Ferozepur Road Salman 0 10,598 11-30-2013 12:48 PM
Last Post: Salman
  CDA to hold three-day auction of 56 commercial plots Salman 0 12,917 11-06-2013 02:58 PM
Last Post: Salman
  Kashmir Highway project: Instead of receiving funds, CDA conducting inquiry Salman 0 8,385 10-31-2013 11:58 AM
Last Post: Salman
  CDA to hold auction of commercial plots Salman 0 11,920 10-10-2013 01:42 PM
Last Post: Salman
  Road From LOS To Multan Road, Construction Work On The Go Salman 0 12,782 09-23-2013 03:18 PM
Last Post: Salman
  Authorities Plan To Build Underpasses And An Overhead Bridge In The DHA Lahore Salman 0 8,645 09-12-2013 08:22 PM
Last Post: Salman
  Illegitimate Allocation Of Rs 1 Billion Funds For Progression Of Kachi Abadis Salman 0 7,769 09-04-2013 08:37 PM
Last Post: Salman
  Motorways funds diverted to big bosses areas, PM informed Salman 0 6,209 07-19-2013 12:13 PM
Last Post: Salman
  CM Punjab To Release Funds For Renovation Of Gawalmandi Food Street Salman 0 4,927 05-10-2013 11:27 AM
Last Post: Salman
  Funds for NHA schemes slashed to Rs 9 billion Salman 0 3,724 05-02-2013 11:30 AM
Last Post: Salman
  Kalma Chowk underpasses open Salman 0 4,915 03-04-2013 11:22 AM
Last Post: Salman
  CDA to auction petrol pump site to boost ‘welfare funds’ Salman 0 4,806 01-10-2013 01:28 PM
Last Post: Salman
  Rawalpindi Developmen News : Funds for projects released Salman 0 4,396 09-27-2012 02:35 PM
Last Post: Salman
  Rawalpindi Development News : Design of Railway underpasses to be handed over to RDA Salman 0 5,392 09-18-2012 02:58 PM
Last Post: Salman
  Peshawar road project delayed for want of funds Salman 0 5,549 08-13-2012 12:36 PM
Last Post: Salman
  Lack of funds halts Rawalpindi uplift projects Salman 0 5,104 08-13-2012 12:35 PM
Last Post: Salman

Forum Jump:


User(s) browsing this thread: 2 Guest(s)