Post Reply 
 
Thread Rating:
  • 0 Vote(s) - 0 Average
  • 1
  • 2
  • 3
  • 4
  • 5
Park Enclave: First progress made after 10 months
05-22-2012, 11:38 AM
Post: #1
Park Enclave: First progress made after 10 months
Park Enclave: First progress made after 10 months


ISLAMABAD, May 21: After a delay of 10 months, the city managers on Monday took the first practical step to lay infrastructure network in the Park Enclave housing scheme by opening bids for construction of the boundary wall.

“The lowest bid was submitted by a construction firm – M. Arif & Co. – as it quoted 19 per cent below the Military Engineering Service (MES) schedule and 10 per cent below the National Highway Authority (NHA) rates of 2009,” said CDA spokesman Ramzan Sajid.

He said a total of 17 construction firms had submitted their bids for the first phase of the development work – construction of boundary wall. Work on the other phases like construction of roads, sewers and drainage network would be initiated very shortly, he added.

It has been learnt that the Capital Development Authority (CDA) has eaten up over 80 per cent of the money generated through the sale of 650 plots in Park Enclave instead of utilising it on laying of the infrastructure.

However, the spokesman quoted the CDA chairman Farkhand Iqbal as saying: “The authority has sufficient funds for the development of the scheme and the work would be executed on a fast pace.”

The chairman said the whole area of Park Enclave had already been demarcated. However, sources in the CDA said the civic agency had so far not addressed the land acquisition issue and locals of Kuri and Majjoan villages (where the scheme is being established) were demanding compensation for their land.

The sources said the project was launched 10 months back (on July 20) but its development work could not be started due to ‘slackness’ of the civic body.

“Under a decision of the CDA board, 40 per cent of the money deposited by the plot owners can be spent on other projects,” the spokesman added.

He said there was no issue of money in the development of the scheme rather it was delayed due to some technical problems.

However, a senior official of the CDA said the authority had collected around Rs2 billion and 80 per cent of it had been spent on payment of employees’ salaries and dues of some contractors.

The CDA sources said another housing project – Sector I-15 – remained in the doldrums only because its money had been spent on different projects like construction of roads, bridges and underpasses in 2005-06. Now the plot seekers in the scheme are demanding reimbursement of their money.

The Park Enclave housing project would involve the construction of 700 houses in phase-I and another 600 houses in phase–II.

Meanwhile, the CDA has completely changed the development plan of Park Enclave and decided to go for traditional development instead of modern infrastructure work as promised at the time of launching of the scheme.

The development plan has been changed after National Engineering Services of Pakistan (Nespak) rejected technical bids of all four pre-qualified construction firms compelling the CDA to go for fresh tendering.
Visit this user's website Find all posts by this user
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  Final Stages of Quetta Safe City Project Signal Progress in Counterterrorism and Poli LRE-Azan 0 549 01-19-2024 06:47 PM
Last Post: LRE-Azan
  Booking is Now Available for Plots in Chahar Bagh Enclave by RUDA LRE-Azan 0 478 11-22-2023 01:00 PM
Last Post: LRE-Azan
  Chief Secretary Orders Swift Digitization of LDA Records within Two Months LRE-Azan 0 531 10-27-2023 01:55 PM
Last Post: LRE-Azan
  Minister Assesses Progress of CPEC Projects in Gwadar LRE-Azan 0 655 10-11-2023 07:16 PM
Last Post: LRE-Azan
  CDA demolishes 48 houses in Park Enclave-I LRE-Azan 0 889 05-20-2023 04:28 PM
Last Post: LRE-Azan
  Lahore Smart City Development: A Spectacular Slideshow of Progress LRE-Azan 0 797 05-17-2023 01:48 PM
Last Post: LRE-Azan
  Lahore Gulberg to Defence Chowk to be Made 5km Signal Free Corridor LRE-Azan 0 1,490 01-01-2022 06:51 PM
Last Post: LRE-Azan
  RUDN Enclave Islamabad | Public Notice LRE-Azan 0 1,444 11-20-2021 02:59 PM
Last Post: LRE-Azan
  Gwadar Would Be Made A Modern Port City of International Standard Salman 0 4,957 07-19-2017 02:15 PM
Last Post: Salman
  CDA DWP approves PC-1 of Park Enclave project Salman 0 4,385 01-23-2014 04:44 PM
Last Post: Salman
  Park Enclave Housing Project, Senate Committee took notice of development Salman 0 6,308 01-08-2014 02:44 PM
Last Post: Salman
  Hurdles in dev of Park enclave housing project to be removed Salman 0 5,496 01-02-2014 01:31 PM
Last Post: Salman
  Park Enclave: A big challenge for CDA boss Salman 0 5,978 12-23-2013 12:38 PM
Last Post: Salman
  Modern burn centre to be functional in 2 months Salman 0 6,528 10-28-2013 03:22 PM
Last Post: Salman
  Lahore :Property Tax And Token Receiving Procedure To Be Made Easy Salman 0 7,861 07-11-2013 12:00 AM
Last Post: Salman
  Bahria Enclave-II not approved, says CDA Salman 0 17,900 06-12-2013 02:21 PM
Last Post: Salman
  Land for road to Bahria Enclave: Official causes Rs5bn loss to CDA Salman 0 8,882 05-29-2013 11:45 AM
Last Post: Salman
  Mini golf club was illegally made: SC asks CDA to take stern action against officers Salman 0 5,773 02-22-2013 07:03 PM
Last Post: Salman
  Allottee made millions by misusing LDA plot leased to set up school Salman 0 4,815 12-27-2012 12:39 PM
Last Post: Salman
  Progress on DHA City projects reviewed Salman 0 4,387 11-28-2012 01:17 PM
Last Post: Salman

Forum Jump:


User(s) browsing this thread: 1 Guest(s)