Pirwadhai Flyover completion unlikely by April 30
04-17-2013, 04:29 PM
Post: #1
Pirwadhai Flyover completion unlikely by April 30
Although Rawalpindi Division Commissioner Khalid Saood Chaudhry has directed authorities concerned to finish the Pirwadhai Flyover Project by April 30, the mega project is likely to end by May 15, sources said.

Khalid visited the site of all three under construction mega projects in the city to review work progress. The commissioner was briefed about the Sixth Road Flyover Project and was informed that the work would be completed by April 25 to April 30. Earlier, the project completion date was given as January 24, which has already been missed by three months. Additionally, the roads under Pirwadhai Flyover are still under construction. Sources said that keeping in view the pace of work, the project was more likely to be completed by May 15 rather than April 30. Khalid has, however, ordered the authorities concerned to wrap up the construction work by April 30 at every cost. - See more at: http://www.pakistantoday.com.pk/2013/04/...Hld1C.dpuf
Visit this user's website Find all posts by this user
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  Emergency and disaster management NOC Mandatory on Building Completion in Capital Isl LRE-Azan 0 941 11-08-2021 08:08 PM
Last Post: LRE-Azan
  CDA chief for speedy completion of parks’ uplift projects Salman 0 3,962 02-25-2014 01:18 PM
Last Post: Salman
  CDA Chairman stresses early completion of Kashmir Highway Salman 0 4,248 02-12-2014 07:48 PM
Last Post: Salman
  KMC Administrator Ordains Early Completion Of Flyovers Salman 0 4,572 10-23-2013 12:22 PM
Last Post: Salman
  Delay in completion of project irks Pindiites Salman 0 6,749 09-30-2013 03:45 PM
Last Post: Salman
  Timely completion of projects being ensured: CM Salman 0 9,554 08-03-2013 12:55 PM
Last Post: Salman
  CDA chairman for immediate completion of projects Salman 0 4,857 06-24-2013 11:38 AM
Last Post: Salman
  Need for early completion of Lyari expressway project stressed Salman 0 4,727 06-20-2013 12:37 PM
Last Post: Salman
  Deadline for completion of half part of Mareer Chowk expansion project extended Salman 0 4,064 05-24-2013 01:05 PM
Last Post: Salman
  Pirwadhai underpass opened to traffic, but flyover still closed Salman 0 3,835 03-22-2013 08:40 PM
Last Post: Salman
  Work at Pirwadhai Flyover stalled Salman 0 3,119 02-04-2013 11:45 AM
Last Post: Salman
  Pirwadhai Mor Flyover faces bottleneck Salman 0 3,256 01-10-2013 01:27 PM
Last Post: Salman
  Metro bus project nears completion’ Salman 0 4,287 12-31-2012 12:37 PM
Last Post: Salman
  CM assures timely completion of Metro Bus Project Salman 0 6,020 11-20-2012 12:11 PM
Last Post: Salman
  Early completion of Bari Imam Complex ordered Salman 0 5,288 11-09-2012 01:24 PM
Last Post: Salman
  December 15 deadline set for completion of development projects in Pindi Salman 0 4,842 11-06-2012 01:34 PM
Last Post: Salman
  Timely completion of Margalla Avenue demanded Salman 0 5,126 10-11-2012 11:43 AM
Last Post: Salman
  Early completion of Lyari expressway demanded Salman 0 4,800 08-27-2012 06:09 PM
Last Post: Salman
  CDA official directed for early completion of Bari Imam complex Salman 0 4,769 07-27-2012 11:40 AM
Last Post: Salman
  Minister directs PHA to give clear-cut completion timeframe Salman 0 4,635 07-19-2012 12:34 PM
Last Post: Salman

Forum Jump:


User(s) browsing this thread: 2 Guest(s)