CDA likely to face problems due to delay in land acquisition
CDA likely to face problems due to delay in land acquisition

Islamabad :Delay on part of the Capital Development Authority (CDA) in starting acquisition of land would create problems for it to open and develop two new sectors — C-15 and C-16 — in near future.

Sources in the civic body said that CDA Chairman Farkhand Iqbal wanted to open two new sectors during the financial year 2012-2013, but there was lack of planning to take possession of open land, the award of which was announced about five years back.

“The CDA should acquire open land as early as possible to avoid construction of Built-up Property (BuP) there,” a senior official of the CDA said, adding that otherwise these two sectors would also face the fate like that of sectors D-12 and G-14.

It has been noted that BuPs on the land of new sectors were created due to the negligence or with the connivance of officials of the CDA and Islamabad Capital Territory (ICT) and they themselves were responsible for causing undue delay in development of these sectors.

Currently, there are only a few BuPs, which are scattered on the land of two new sectors, and they will increase with the passage of time till the CDA acquires and takes possession of land.

Meanwhile, sources said that the CDA chairman, a few days back, chaired a meeting to discuss details with regard to launching of sectors C-15 and C-16, but it ended without taking any decision. The meeting was attended by Member Planning Abdul Aziz Qureshi, Member Estate Khalid Mehmud Mirza and Director-General Planning Sardar Sindhu.

The CDA member estate, however, told the chairman that he would soon present a plan before the CDA Board on the land acquisition.It has also been learnt that the CDA Board had already approved the layout plan of two sectors.

According to the plan, the provision of commercial plots had been made along Margalla Avenue, while for the first time, some plots have been reserved for guesthouses and hostels for boys and girls. There would be five or six plots for guesthouses and four plots for hostels (boys and girls) to avert non-conforming use of residential buildings as being witnessed in the developed sectors.

The Sector C-15 would have 4,000 residential plots, measuring 40x80 square feet and 500 square yards. Similarly, the Sector C-16 would have 4,300 plots of sizes 25x50, 30x60 and 40x80 square feet and 500 square yards.
Visit this user's website Find all posts by this user
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  Property Registration: Authorities Disobeying FBR Orders could Face Fines of up to Rs LRE-Azan 0 1,611 12-02-2021 07:50 PM
Last Post: LRE-Azan
  New City at Ravi Bank: Acquisition of one Lac Acres of Land Became a Challenge LRE-Azan 0 1,565 11-22-2021 08:05 PM
Last Post: LRE-Azan
  Islamabad: FGEHA Asked to Provide Details of Land Acquisition in G-14 LRE-Azan 0 1,536 11-02-2021 06:34 PM
Last Post: LRE-Azan
  Land acquisition for motorway complete, says DCO Salman 0 5,841 04-21-2015 02:42 PM
Last Post: Salman
  Development projects face delay due to rains Salman 0 6,206 03-31-2014 07:36 PM
Last Post: Salman
  Punjab approves Rs 3,315 million for Apparel Park land acquisition Salman 0 5,820 03-31-2014 07:32 PM
Last Post: Salman
  Minister dissatisfied over delay in Kurri Road project Salman 0 5,004 02-25-2014 01:16 PM
Last Post: Salman
  Garment City’s Land Acquisition Stayed Salman 0 4,744 01-30-2014 04:52 PM
Last Post: Salman
  Delay in approval of building plans by CDA irks investors Salman 0 7,590 11-29-2013 01:17 PM
Last Post: Salman
  Land Department Plans To Develop Nurseries At Railways Land Salman 0 8,760 11-11-2013 04:57 PM
Last Post: Salman
  LDA Directorate of Land Acquisition established Salman 0 5,560 10-21-2013 06:25 PM
Last Post: Salman
  Delay in completion of project irks Pindiites Salman 0 7,276 09-30-2013 03:45 PM
Last Post: Salman
  Delay in widening of Kashmir Highway causing traffic jams Salman 0 9,907 08-01-2013 12:45 PM
Last Post: Salman
  CDA officers face stay order on plot allotment Salman 0 6,270 04-12-2013 12:54 PM
Last Post: Salman
  Delay in DHA Valley irks investors Salman 0 5,858 02-28-2013 03:00 PM
Last Post: Salman
  Late payments delay project Salman 0 4,010 02-18-2013 06:54 PM
Last Post: Salman
  Benazir Bhutto Road Becomes Centre Of Problems Salman 0 5,085 02-09-2013 12:50 PM
Last Post: Salman
  Delay in 6th Road flyover feared Salman 0 4,230 12-15-2012 05:20 PM
Last Post: Salman
  Delay in Chohar Chowk expansion protested Salman 0 5,126 10-18-2012 02:04 PM
Last Post: Salman
  Land use: Housing on agri-land to be referred to 2nd committee Salman 0 4,691 09-04-2012 02:13 PM
Last Post: Salman

Forum Jump:


User(s) browsing this thread: 1 Guest(s)