Post Reply 
 
Thread Rating:
  • 0 Vote(s) - 0 Average
  • 1
  • 2
  • 3
  • 4
  • 5
Deadline of Metro Bus Project extended
09-25-2014, 02:15 PM
Post: #1
Deadline of Metro Bus Project extended
Rawalpindi : The sit-ins of Pakistan Tehreek-e-Insaaf (PTI) and Pakistan Awami Tehreek (PAT) on one hand have caused loss of billions of rupees to the country while on the other affected construction work on the Metro Bus Service Project, particularly in Islamabad.

As work has been going on at a snail’s pace, the project would not be completed on its scheduled time of December 25.

Metro Bus Service Project Implementation Committee Chairman Hanif Abbasi told ‘The News’ in an exclusive interview here on Tuesday that now the completion period of the project has been extended by two months. It is likely to be completed by the end of February, he stated. However, the meeting of the new deadline depends on improvement of situation, which is not normal at present due to presence of PTI and PAT activists in the Red Zone, he stated. “If PTI and PAT workers as well as their leaders end their sit-ins only then it will become possible for us to meet the new deadline of February 2015,” Abbasi cleared.

The work on the project started to get affected with the arrival of PTI and PAT supporters on August 14, which is till now going at a very slow pace. The leadership of the two parties should realise that the project after its completion would benefit the residents of Islamabad and Rawalpindi as over 150,000 people would utilise Metro buses daily at a nominal fare of Rs20 per head from starting point to termination point. “Otherwise the fares of public transport plying on roads these days are very high as transporters are charging Rs40 per head from Saddar (Rawalpindi) to Pakistan Secretariat (Islamabad). The PTI and PAT activists should vacate the routes where work on the project has to be carried out. Currently they are sitting in frames 4 and 5 of the project where no work could be carried out,” said the PML-N leader.

He alleged that the PTI and PAT activists caused immense loss to the machinery and other equipment, including vehicles, placed at the site of the project where work was to be done. “The condition of the machinery and equipment, which are very expensive, has deteriorated. Similarly, tools are also missing from the project sites at frames 4 and 5 at the D-Chowk,” he added. He said that helmets used by labourers are missing and PAT chief Dr. Tahirul Qadri had been seen wearing one of those helmets,” Abbasi said.

However, construction work on the Faizabad-Mall Road section of the project is being carried out smoothly. The work on installation of girders on pillars is being carried out at different sections of the project in Rawalpindi, Abbasi said. He said that they have been able to get stay orders vacated for H-9 and depot site at Peshawar Road where seven-storey building of Metro Bus Service Project would be built. Besides ground floor, two storeys would be meant for parking of buses. The offices of the Metro Bus Service Project would be set up on two storeys and one storey would be used for commercial purposes.
Visit this user's website Find all posts by this user
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  Lahore Smart City File Cancellation Date Extended LRE-Azan 0 609 06-02-2023 06:05 PM
Last Post: LRE-Azan
  DHA Quetta Has Extended Date For Conversion Of Affidavit Files To Allocation Till 1st LRE-Azan 0 1,128 02-02-2022 06:47 PM
Last Post: LRE-Azan
  DHA Quetta Has Extended Date For Conversion Of Affidavit Files To Allocation Till 1st LRE-Azan 0 1,157 02-02-2022 06:13 PM
Last Post: LRE-Azan
  LDA City Lahore Extends Deadline To Pay Development Charges LRE-Azan 0 2,034 04-22-2020 08:34 PM
Last Post: LRE-Azan
  DHA Multan Latest News | Conversion of Affidavit to Allocation Date Extended LRE-Azan 0 2,526 11-30-2018 08:23 PM
Last Post: LRE-Azan
  DHA Gujranwala 5 Marla Plots – 1st Installment Payment Deadline & Instruction LRE-Azan 0 3,160 07-02-2018 06:12 PM
Last Post: LRE-Azan
  Orange Line Metro Train Project Lahore Latest Development images LRE-Azan 0 5,572 05-12-2018 01:16 PM
Last Post: LRE-Azan
  SECP yet to finalise answers to objections on Multan Metro project Salman 0 2,384 11-09-2017 01:38 PM
Last Post: Salman
  Project plan for Peshawar Metro Bus finalised Salman 0 2,755 02-07-2017 12:06 PM
Last Post: Salman
  Project plan for Peshawar Metro Bus finalised Salman 0 2,511 02-07-2017 11:56 AM
Last Post: Salman
  Underground Tunnel Progress (Metro Train Project) Salman 0 3,240 09-08-2016 12:01 PM
Last Post: Salman
  Orange Line Metro Project (Arch Bridge) Salman 0 3,149 09-06-2016 04:05 PM
Last Post: Salman
  Remand of DHA City scam accused extended Salman 0 2,824 02-08-2016 02:20 PM
Last Post: Salman
  FGEHF Membership Last Date Extended for Govt Employees Till Jan 30 2016 Salman 0 3,679 01-08-2016 12:13 PM
Last Post: Salman
  Metro train project: LDA to deposit Rs13.17bn after property assessment Salman 0 3,044 10-21-2015 06:22 PM
Last Post: Salman
  CDA gives 10-day deadline to owners Salman 0 2,712 09-21-2015 03:11 PM
Last Post: Salman
  Metro train project will be ‘speedily completed’, says CM Salman 0 3,509 08-13-2015 12:56 PM
Last Post: Salman
  Environment Department approves orange line metro project on certain conditions Salman 0 3,345 08-03-2015 01:41 PM
Last Post: Salman
  Shahbaz Sharif Seeks Reports on Metro Bus Project Salman 0 3,259 05-29-2015 06:13 PM
Last Post: Salman
  Rs165.2 bn Lahore Orange Line Metro Train project cleared Salman 0 3,759 05-07-2015 05:59 PM
Last Post: Salman

Forum Jump:


User(s) browsing this thread: 1 Guest(s)