Park Enclave uplift suffers setback
06-16-2012, 01:06 PM
Post: #1
Park Enclave uplift suffers setback
Park Enclave uplift suffers setback

ISLAMABAD – The development of Park Enclave has suffered another setback after the affectees of Mouza Majoohan, a village falls in Phase-I of the Park Enclave, hampered the contractor to initiate construction work of boundary wall of the housing society, on the ground of non-payment of compensation against their built-up properties.

On Friday, CDA was supposed to kick off the construction work of the Package-I of the project that includes the construction of boundary wall of Park Enclave.

Rs48 million contract of boundary wall has recently been awarded to firm M/s Arif and Co, who has quoted the lowest bid 19 percent below the Military Engineering Services (MES) schedule and 10 per cent below the NHA CSR 2009.

There are 13 BUP (built-up property) structures in Mouza Majoohan falling in Phase-I of the Park Enclave. CDA Board during its meeting held on December 12, 2011 has approved a total compensation of Rs 2,356,189 against 13 structures.

Though it was decided that compensation amount would be paid at earliest to remove hindrances in the smooth execution of the project, till to date the affectees are waiting for it.

On Friday when contractor along with machinery rushed to the site, a group of affectees interrupted them and asked that they (affectees) would not allow any construction activity in the area until the payment of compensation to them.

The episode shows the seriousness of the city managers in terms of execution of this much-delayed project. The frivolous approach of the city managers towards resolving the longstanding issues pertaining to the development of Park Enclave is evident from this latest episode which is furthering the reservations of investors, who are now refusing to pay instalments of plots until visible development on the site.

Meanwhile, a recent decision of the CDA Board that provides diversion of funds collected by the Authority on the account of cost of land from allottees to run Authority’s day-to-day affairs has put a question mark against CDA’s fast sinking credibility.

On the other hand the investors are demanding reimbursement of their money that they have paid so far. By the end of January 2012, CDA had received Rs 1734.38 million from 650 applicants on account of price of plots in Park Enclave Scheme. But in fact the Authority has already drawn 80 percent of the collected amount from Park Enclave accounts.

A spokesperson of the Authority said in the backdrop of affectees protest, the Chairman CDA has directed the Finance Wing of the Authority to expedite the process of payment of compensation to affectees. He said contractor would initiate work on the site on Monday as compensation amount is expected to be released on the same day.
Visit this user's website Find all posts by this user
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  Government Initiates Activation of $1.5 Billion Uplift Fund LRE-Azan 0 620 01-09-2024 03:32 PM
Last Post: LRE-Azan
  Booking is Now Available for Plots in Chahar Bagh Enclave by RUDA LRE-Azan 0 485 11-22-2023 01:00 PM
Last Post: LRE-Azan
  CDA demolishes 48 houses in Park Enclave-I LRE-Azan 0 896 05-20-2023 04:28 PM
Last Post: LRE-Azan
  RUDN Enclave Islamabad | Public Notice LRE-Azan 0 1,453 11-20-2021 02:59 PM
Last Post: LRE-Azan
  Prime Minister orders uplift of infrastructure at Murree Salman 0 4,897 03-01-2014 01:23 PM
Last Post: Salman
  CDA chief for speedy completion of parks’ uplift projects Salman 0 4,617 02-25-2014 01:18 PM
Last Post: Salman
  ICCI criticises CDA for not doing uplift work in markets Salman 0 4,452 02-17-2014 01:18 PM
Last Post: Salman
  PC-1 approval revives hopes for early start of uplift work Salman 0 4,754 02-11-2014 12:25 PM
Last Post: Salman
  CDA DWP approves PC-1 of Park Enclave project Salman 0 4,393 01-23-2014 04:44 PM
Last Post: Salman
  Rs 15m approved for uplift of public parks in capital Salman 0 4,599 01-16-2014 01:52 PM
Last Post: Salman
  Park Enclave Housing Project, Senate Committee took notice of development Salman 0 6,316 01-08-2014 02:44 PM
Last Post: Salman
  Hurdles in dev of Park enclave housing project to be removed Salman 0 5,504 01-02-2014 01:31 PM
Last Post: Salman
  Park Enclave: A big challenge for CDA boss Salman 0 5,992 12-23-2013 12:38 PM
Last Post: Salman
  CDA suffers setbacks in parking plazas project Salman 0 6,257 12-04-2013 01:36 PM
Last Post: Salman
  CM Punjab approves uplift projects worth Rs 12bn Salman 0 7,724 11-29-2013 01:15 PM
Last Post: Salman
  PWD uplift projects: National Assembly panel concerned at embezzlement Salman 0 7,619 11-28-2013 12:58 PM
Last Post: Salman
  Sector I-15: CDA shelves uplift plan Salman 0 9,334 11-09-2013 04:29 PM
Last Post: Salman
  Punjab government approves over Rs 29,753 million uplift schemes Salman 0 7,789 10-30-2013 01:30 PM
Last Post: Salman
  CDGL acquires 4,000 kanals for Ravi bank uplift project Salman 0 8,068 10-25-2013 12:22 AM
Last Post: Salman
  Housing officials ordered to expedite uplift projects Salman 0 5,287 06-12-2013 02:21 PM
Last Post: Salman

Forum Jump:


User(s) browsing this thread: 1 Guest(s)