Post Reply 
 
Thread Rating:
  • 0 Vote(s) - 0 Average
  • 1
  • 2
  • 3
  • 4
  • 5
ISLAMABAD: VVIP movement impeding work on Islamabad Highway
06-21-2008, 10:34 AM
Post: #1
ISLAMABAD: VVIP movement impeding work on Islamabad Highway
ISLAMABAD: CDA Engineering Member Moeen Uddin Kakakhel has said work on Islamabad Highway is in full swing and the 10-lane Islamabad Expressway -- the new name of Islamabad Highway -- will be opened to traffic until the next October.

The project was started in April after three months of its formal groundbreaking on January 30, 2008. The managing director of the construction company, Nadeem Khan, Friday said the work on the 8-kilometre road would be completed in one year with a total cost of Rs 877 million. He said the construction plan had been revised after the groundbreaking and the number of lanes was increased from eight to ten. He said 36.7 of percent work had been completed and they would be able to complete the work ahead of the stipulated time. Khan said the VVIP movement was badly affecting construction. He said though they had a proper security clearance system for labourers, they were not allowed to work during VVIP movement. He said if the practice continued it could delay the project's completion for at least two months. On the other hand, the commuters are suffering from jams owing to heavy traffic on the road. Thousands of vehicles use the road to enter or exit the capital city. There is no alternative route for traffic, which is adding to commuting woes. Amer, a commuter, said the pace of work was satisfactory but traffic jams due to ill-management were nightmarish.

VVIP movement impeding work on Islamabad Highway



Habib Asgher

ISLAMABAD: CDA Engineering Member Moeen Uddin Kakakhel has said work on Islamabad Highway is in full swing and the 10-lane Islamabad Expressway -- the new name of Islamabad Highway -- will be opened to traffic until the next October.

The project was started in April after three months of its formal groundbreaking on January 30, 2008. The managing director of the construction company, Nadeem Khan, Friday said the work on the 8-kilometre road would be completed in one year with a total cost of Rs 877 million. He said the construction plan had been revised after the groundbreaking and the number of lanes was increased from eight to ten. He said 36.7 of percent work had been completed and they would be able to complete the work ahead of the stipulated time. Khan said the VVIP movement was badly affecting construction. He said though they had a proper security clearance system for labourers, they were not allowed to work during VVIP movement. He said if the practice continued it could delay the project's completion for at least two months. On the other hand, the commuters are suffering from jams owing to heavy traffic on the road. Thousands of vehicles use the road to enter or exit the capital city. There is no alternative route for traffic, which is adding to commuting woes. Amer, a commuter, said the pace of work was satisfactory but traffic jams due to ill-management were nightmarish.

VVIP movement impeding work on Islamabad Highway



Habib Asgher

ISLAMABAD: CDA Engineering Member Moeen Uddin Kakakhel has said work on Islamabad Highway is in full swing and the 10-lane Islamabad Expressway -- the new name of Islamabad Highway -- will be opened to traffic until the next October.

The project was started in April after three months of its formal groundbreaking on January 30, 2008. The managing director of the construction company, Nadeem Khan, Friday said the work on the 8-kilometre road would be completed in one year with a total cost of Rs 877 million. He said the construction plan had been revised after the groundbreaking and the number of lanes was increased from eight to ten. He said 36.7 of percent work had been completed and they would be able to complete the work ahead of the stipulated time. Khan said the VVIP movement was badly affecting construction. He said though they had a proper security clearance system for labourers, they were not allowed to work during VVIP movement. He said if the practice continued it could delay the project's completion for at least two months. On the other hand, the commuters are suffering from jams owing to heavy traffic on the road. Thousands of vehicles use the road to enter or exit the capital city. There is no alternative route for traffic, which is adding to commuting woes. Amer, a commuter, said the pace of work was satisfactory but traffic jams due to ill-management were nightmarish.

VVIP movement impeding work on Islamabad Highway
Find all posts by this user
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  CDA Unveils Blueprint for Model Village Project in Islamabad Capital Territory LRE-Azan 0 606 01-17-2024 06:13 PM
Last Post: LRE-Azan
  Finance Minister Unveils Export-Import Bank (EXIM) in Islamabad LRE-Azan 0 511 12-22-2023 06:36 PM
Last Post: LRE-Azan
  CDA Proposes New Dam Project to Meet Islamabad Water Demand LRE-Azan 0 610 10-13-2023 07:55 PM
Last Post: LRE-Azan
  Islamabad: FBR Initiates Nationwide Campaign to Enhance Tax Collection and Combat Eva LRE-Azan 0 602 09-14-2023 04:27 PM
Last Post: LRE-Azan
  CDA shares list of hundreds of illegal buildings, construction projects in Islamabad LRE-Azan 0 809 08-24-2023 06:08 PM
Last Post: LRE-Azan
  CDA to introduce 130 electric buses in Islamabad LRE-Azan 0 657 08-24-2023 06:06 PM
Last Post: LRE-Azan
  Upcoming Green Spaces: CDA's Ambitious Plan for New Parks in Islamabad LRE-Azan 0 640 08-19-2023 02:09 PM
Last Post: LRE-Azan
  CDA To Invite Tenders For The Development Of Sector C-16 Islamabad* LRE-Azan 0 934 04-29-2023 06:14 PM
Last Post: LRE-Azan
  After a protracted 7 years, CDA resumes development in Sector C-15 in Islamabad LRE-Azan 0 829 04-03-2023 06:19 PM
Last Post: LRE-Azan
  Park View City Islamabad Ramzan Discount Offer 2023 LRE-Azan 0 904 03-25-2023 06:11 PM
Last Post: LRE-Azan
  CDA Plans to Build Affordable Hostels in Islamabad LRE-Azan 0 998 02-11-2023 05:48 PM
Last Post: LRE-Azan
  Islamabad Govt to Revise the ICT Master Plan to Create New Sanitary Landfill Sites LRE-Azan 0 927 02-11-2023 05:48 PM
Last Post: LRE-Azan
  Investment in 5-Marla Houses for Sale in Islamabad on Installments LRE-Azan 0 861 01-26-2023 02:42 PM
Last Post: LRE-Azan
  Avail Huge Discounts On Installments Projectes In Islamabad Housing Schemes LRE-Azan 0 1,293 01-24-2023 05:45 PM
Last Post: LRE-Azan
  (CDA) NHA Employees Residential Apartments Housing Project Islamabad Approved LRE-Azan 0 1,224 01-24-2023 03:16 PM
Last Post: LRE-Azan
  Islamabad Fails to Find Permanent Landfill Site, Consultant Engaged January,21,2023 LRE-Azan 0 1,059 01-21-2023 01:18 PM
Last Post: LRE-Azan
  ISLAMABAD News : CDA likely to approve establishment of economic zone near Rawat LRE-Azan 0 950 01-16-2023 07:33 PM
Last Post: LRE-Azan
  Allottees move SC over housing schemes in F-14, F-15 of Islamabad LRE-Azan 0 1,682 02-24-2022 08:21 PM
Last Post: LRE-Azan
  Islamabad: 5 Accused including CDA Officers Jailed, Fined Billion of Rupees LRE-Azan 0 1,670 02-02-2022 07:10 PM
Last Post: LRE-Azan
  Islamabad: The Return on Investment in National Savings Schemes has Increased LRE-Azan 0 1,581 12-11-2021 07:54 PM
Last Post: LRE-Azan

Forum Jump:


User(s) browsing this thread: 1 Guest(s)