Post Reply 
 
Thread Rating:
  • 0 Vote(s) - 0 Average
  • 1
  • 2
  • 3
  • 4
  • 5
Mangla repairs to take two months, at least
07-01-2009, 05:18 AM
Post: #1
Mangla repairs to take two months, at least
By Umer Bhatti
LAHORE: The Monday’s short-circuiting of 10 turbines at the Mangla Hydro Power Station will take at least two months for repair, The News has learnt.

The entire power plant came to a grinding halt after the mishap, which, the sources revealed, was the result of Mangla managers’ attempt to push the worn-out system beyond limits, taking the total generation to 1,150 MW against the normal 1,000 MW. The original ‘oil-filled’ cables, having outlived their utility, could not survive the extra load, leading to the disaster. The Wapda had already awarded the tender for the replacement of these underground oil-filled cables. These cables, joining the turbines with the national grid, had a lifespan of 30 years and should have been replaced till 1997.

The sources said initially the cables of two turbines heated up due to overloading, leading to spark in one of the turbines, which turned into a full-blown fire. The sources also said that the Wapda authorities were repeatedly informed by the officials of the Mangla Dam project to replace these cables to avoid any future setback, but the hierarchy gave a deaf ear to these requests.

The issue of replacing the oil-filled cables, the sources revealed, was taken up some two years ago, and finally the Wapda considered two companies — M/s SGWI and Excel Technological Services (ETS) — to award the contract in February 2008. The contract was finally awarded to ETS in February 2009. Ironically, the work on the project was yet to begin.

The total length of the tunnel, having all the cables, is one kilometre. Managing Director Pepco Tahir Basharat Cheema has said “we are going to lay the overhead cable, which would hasten the recovery process and save time”. But experts say it would take around 3-4 months even if the cables were installed overhead. It was also learnt there was no local expertise available in the country so the expertise had to be called from abroad.

Sources in the Wapda claimed the authority did not have the power cable in hand and planning to import it from Saudi Arabia. According to a former member Wapda, if the cables in any of the turbine in a power station get overloaded, there exist certain instruments called ‘Protection Relays’, which should be operated right after an emergency occurs. He said these relays were battery-operated and it is possible that the batteries were not charged or the ‘Protection Relays’ were out of work altogether. The News made a number of calls to get the version of Wapda Chairman Shakil Durrani and other officials but no one attended the calls. The story of CD’s evaluation of foreign gifts

http://www.thenews.com.pk/top_story_detail.asp?Id=23032
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  Chief Secretary Orders Swift Digitization of LDA Records within Two Months LRE-Azan 0 536 10-27-2023 01:55 PM
Last Post: LRE-Azan
  Modern burn centre to be functional in 2 months Salman 0 6,534 10-28-2013 03:22 PM
Last Post: Salman
  Park Enclave: First progress made after 10 months Salman 0 5,369 05-22-2012 11:38 AM
Last Post: Salman
  Sinking in: Repairs to depressed Ring Road underway Salman 0 4,055 04-13-2012 12:32 PM
Last Post: Salman
  Dilapidated Swan Road awaits repairs Salman 0 3,360 03-12-2012 12:33 PM
Last Post: Salman
  ‘Development of stalled sectors to start in three months’ Lahore_Real_Estate 0 4,116 03-01-2012 01:10 PM
Last Post: Lahore_Real_Estate
  Park Enclave dev work to be completed within 18 months Lahore_Real_Estate 0 4,251 02-21-2012 11:59 AM
Last Post: Lahore_Real_Estate
  17% tax revenue increase achieved in last six months Salman 0 4,340 01-14-2012 02:52 PM
Last Post: Salman
  ‘Country to get $2.5bn foreign exchange in coming months’ Salman 0 4,508 01-14-2012 02:51 PM
Last Post: Salman
  CDA promises to hand over possession of plots in eighteen months Salman 0 4,591 01-06-2012 12:48 PM
Last Post: Salman
  Islamabad: CDA Park Enclave project to be completed in 18 months Lahore_Real_Estate 0 3,983 12-01-2011 01:49 PM
Last Post: Lahore_Real_Estate
  Gilani to open Mangla Dam raising project Lahore_Real_Estate 0 3,843 10-11-2011 12:40 PM
Last Post: Lahore_Real_Estate
  CDGK to complete Mehran Highway in six months Lahore_Real_Estate 0 4,156 10-11-2011 11:35 AM
Last Post: Lahore_Real_Estate
  Three months later, Elahi still not deputy prime minister Lahore_Real_Estate 0 3,864 08-06-2011 12:33 PM
Last Post: Lahore_Real_Estate
  Exports of Rs1,722,691 million recorded in 10 months Lahore_Real_Estate 0 3,572 05-21-2011 11:47 AM
Last Post: Lahore_Real_Estate
  Over 50,000 applicants waiting for months to get passports Lahore_Real_Estate 0 3,617 04-18-2011 12:58 PM
Last Post: Lahore_Real_Estate
  No new gas connection to be issued for six months Lahore_Real_Estate 0 4,271 04-18-2011 12:54 PM
Last Post: Lahore_Real_Estate
  300 new industrial units to be set up in 15 months Lahore_Real_Estate 0 3,852 09-02-2010 03:00 PM
Last Post: Lahore_Real_Estate
  Mohlanwal Punjab Govt Employees Housing Scheme payment time extended for 3 months Lahore_Real_Estate 0 7,314 07-12-2010 04:30 PM
Last Post: Lahore_Real_Estate
  Pak Parlimentarians: PHD in 2 Months...! LRE 0 3,666 05-28-2010 01:05 AM
Last Post: LRE

Forum Jump:


User(s) browsing this thread: 1 Guest(s)