Post Reply 
 
Thread Rating:
  • 0 Vote(s) - 0 Average
  • 1
  • 2
  • 3
  • 4
  • 5
Slow work on power transmission projects: ADB warns of partial loan cancellation
09-07-2009, 07:15 PM
Post: #1
Slow work on power transmission projects: ADB warns of partial loan cancellation
MUSHTAQ GHUMMAN
ISLAMABAD (September 07 2009): The Asian Development Bank (ADB) has threatened to cancel part of the loan for power transmission, enhancement investment programme, tranche 2, if procurement process is not completed on time, official sources told Business Recorder.

The Bank said that the overall implementation progress of the project has generally been slow. As of July 31, 2009, physical progress achieved was estimated at 13 percent, compared with the elapsed loan period of 21 percent. Cumulative contract awards and disbursements achieved are $41.8 million and $11.7 million, or 30 percent and 19 percent of the 2009 projections of $140 million and $62.5 million, respectively, which were jointly prepared at the beginning of the year.

Pil-Bae Song, a Director of the ADB, in a letter to Tariq Qazi, Chief Executive, National Transmission and Dispatch Company (NTDC), observed that progress on procurement was significantly behind schedule and if the majority of the civil works contracts could not be awarded by the end of 2009 completion of all sub-projects by end-2013 would be at high risk.

"As has been extensively discussed, the current practice of procuring civil works, materials and equipment through multiple contract packages and diversified lots increases processing time and load for both NTDC and ADB and eventually slows down project implementation," he said.

There are 15 contract packages remaining, including civil works and supply of material and equipment to be procured. One option would be to club the remaining contracts into the following four packages: (i) civil works for grid stations at T T. Singh, Okara, and Ghazi Barotha, on turnkey basis; (ii) civil works for 220 kv transmission lines; (iii) SVC installation at Quetta on turnkey basis; and (iv) procurement of materials and equipment. Procurement of 4 contract packages instead of 15 would clearly save cost as well as time. "We need to take prompt action to ensure timely processing of procurement, failing which, may risk partial cancellation of the items that are not procured in time. Also, ADB's approval for further tranches would be more difficult since the delays would be seen as lack of absorptive capacity," he concluded.

Copyright Business Recorder, 2009


http://www.brecorder.com/index.php?id=95...=&supDate=
Find all posts by this user
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  China rolls over $2bn loan to Pakistan: Foreign Minister Ishaq Dar LRE-Azan 0 1,009 04-01-2023 01:02 PM
Last Post: LRE-Azan
  NHA Work on 17 Road Infrastructure Projects is continuing in backward Areas LRE-Azan 0 4,904 01-17-2018 05:24 PM
Last Post: LRE-Azan
  State Bank Remove Loan Limit for Real Estate Sector Salman 0 6,206 01-07-2014 02:29 PM
Last Post: Salman
  Minister for expediting work on 7 PHAF projects Salman 0 5,523 12-19-2013 11:54 AM
Last Post: Salman
  CDA asked to expedite work on ICT development projects Salman 0 8,712 09-02-2013 12:43 PM
Last Post: Salman
  CDA directed to expedite work on development projects Salman 0 9,215 08-16-2013 11:58 AM
Last Post: Salman
  Nandipur power project : Chinese company agrees to resume work on CM’s prodding Salman 0 7,219 07-06-2013 05:19 PM
Last Post: Salman
  LDA warns dodgy name users Salman 0 3,964 02-08-2013 01:31 PM
Last Post: Salman
  LDA warns dodgy name users Salman 0 3,731 02-07-2013 06:56 PM
Last Post: Salman
  LDA warns developers and builders Salman 0 4,265 01-26-2013 01:51 PM
Last Post: Salman
  Legal hurdles slow down CDA legal actions Salman 0 3,800 12-26-2012 12:22 PM
Last Post: Salman
  Work on DHA projects to be accelerated Salman 0 4,250 11-28-2012 01:16 PM
Last Post: Salman
  German investment in Punjab power projects safe: Shahbaz Salman 0 4,996 10-06-2012 11:15 PM
Last Post: Salman
  LDA warns of illegal housing colony Salman 0 5,052 08-23-2012 12:29 PM
Last Post: Salman
  Housing Ministry asked to expedite work on ongoing projects Salman 0 5,385 07-19-2012 12:37 PM
Last Post: Salman
  Energy Department set up to help launch power projects Salman 0 4,238 05-29-2012 03:08 PM
Last Post: Salman
  NHA Demands Early Funds Release To Restart Work On Delayed Projects Salman 0 4,965 05-12-2012 02:30 PM
Last Post: Salman
  Steps taken to expedite work on development projects Salman 0 5,092 05-04-2012 01:29 PM
Last Post: Salman
  1,000MW wind power projects: Sindh govt assures AEDB of allocating land for projects Salman 0 6,595 04-24-2012 12:14 PM
Last Post: Salman
  CDA seeks loan for LED project Salman 0 3,847 03-15-2012 01:12 PM
Last Post: Salman

Forum Jump:


User(s) browsing this thread: 1 Guest(s)