The following warnings occurred:
Warning [2] count(): Parameter must be an array or an object that implements Countable - Line: 802 - File: showthread.php PHP 7.4.29 (Linux)
File Line Function
/showthread.php 802 errorHandler->error





Post Reply 
 
Thread Rating:
  • 0 Vote(s) - 0 Average
  • 1
  • 2
  • 3
  • 4
  • 5
‘Slow response of utilities causing delay in SFC-III’
08-07-2009, 06:29 AM
Post: #1
‘Slow response of utilities causing delay in SFC-III’
By Gibran Ashraf

The delay in the completion of Signal Free Corridor (SFC)-III, especially in the construction of elevated u-turns at Safari Park and at Metro, has been due to ‘the slow reaction’ of utilities, said Engr. Taha of the Works and Services Department of the City District Government Karachi (CDGK).

Taha, who is the in-charge of the construction of the bridge at Samama Shopping mall, said that despite their best efforts to coordinate with other utility services, including the Karachi Water and Sewerage Board (KWSB), Karachi Electric Supply Company (KESC), Sui Gas, and Pakistan Telecommunciations Corporation Limited (PTCL), the lethargy shown by these utilities delayed the project. “Work started on March 22. If there had been no problems, I would have completed my work in a total of three working months. However, this is the fourth working month, and there is still much to do.”

“The Samama Bridge, being built at a cost of 250 million rupees, was put up in just 76 days.

However, it cannot be termed complete till the service lane adjacent to it is not finished.” It is here, according to Taha, that problems begin to surface: the KWSB needs to replace a 24-inch line from Safari Park to Samama. Until and unless that line is not installed, the road cannot be completed, carpeted, and the valves, drains, and manholes cannot be aligned.

Then there is the Rs22million-worth elevated u-turn at Safari Park and the Rs16million-worth elevated u-turn at Abul Hasan Ispahani road. Work on these u-turns stalled due to hindrances in land acquisition near Madhu Goth from the Land authority, while there were delays with the KESC, as work on power lines that needed to be moved commences as late as July 26.

Then there were also problems with strikes, especially those of transportation, but perhaps the biggest impediment was the damage caused by torrential downpour in the city, due to which works at some parts had to be redone. Residents had to face the brunt of the inconvenience, as both tracks of University Road in Block 11 have been upended and there is only one entry and exit point for the area.

“Had there been no strikes, rains, I can assure you that the project would have been completed in three working months,” Taha said.

http://www.thenews.com.pk/daily_detail.asp?id=191873
Quote this message in a reply
Post Reply 


Messages In This Thread
‘Slow response of utilities causing delay in SFC-III’ - Naveed Yaseen - 08-07-2009 06:29 AM

Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  Court seeks response from FBR as DHA challenges FED imposition on property LRE-Azan 0 204 09-30-2024 07:00 PM
Last Post: LRE-Azan
  Development projects face delay due to rains Salman 0 6,211 03-31-2014 07:36 PM
Last Post: Salman
  Minister dissatisfied over delay in Kurri Road project Salman 0 5,008 02-25-2014 01:16 PM
Last Post: Salman
  Delay in approval of building plans by CDA irks investors Salman 0 7,592 11-29-2013 01:17 PM
Last Post: Salman
  CDA Receives Minor Response Form Buyers Salman 0 9,048 10-02-2013 08:04 PM
Last Post: Salman
  Delay in completion of project irks Pindiites Salman 0 7,279 09-30-2013 03:45 PM
Last Post: Salman
  Delay in widening of Kashmir Highway causing traffic jams Salman 0 9,909 08-01-2013 12:45 PM
Last Post: Salman
  Delay in DHA Valley irks investors Salman 0 5,861 02-28-2013 03:00 PM
Last Post: Salman
  Late payments delay project Salman 0 4,013 02-18-2013 06:54 PM
Last Post: Salman
  Neglected SITE road continues causing inconvenience Salman 0 4,448 12-28-2012 03:48 PM
Last Post: Salman
  Legal hurdles slow down CDA legal actions Salman 0 3,795 12-26-2012 12:22 PM
Last Post: Salman
  CDA receives lacklustre response from bidders Salman 0 3,894 12-19-2012 05:25 PM
Last Post: Salman
  Delay in 6th Road flyover feared Salman 0 4,234 12-15-2012 05:20 PM
Last Post: Salman
  CDA receives healthy response to auction of plots Salman 0 4,852 11-22-2012 03:16 PM
Last Post: Salman
  Delay in Chohar Chowk expansion protested Salman 0 5,132 10-18-2012 02:04 PM
Last Post: Salman
  CDA likely to face problems due to delay in land acquisition Salman 0 4,593 06-18-2012 01:40 PM
Last Post: Salman
  Energy crisis causing irreparable loss to national economy: CM Salman 0 4,103 04-07-2012 12:15 PM
Last Post: Salman
  Encroachment in commercial market of Satellite Town is causing traffic mess Salman 0 5,088 03-21-2012 02:15 PM
Last Post: Salman
  Toll plazas on Ring road: New taxes on all vehicles Tolling box causing inconvenience Salman 0 5,404 03-17-2012 02:15 PM
Last Post: Salman
  Allottees dismayed over delay in Sector G-14/2-3 development work Lahore_Real_Estate 0 4,353 02-01-2012 01:15 PM
Last Post: Lahore_Real_Estate

Forum Jump:


User(s) browsing this thread: 1 Guest(s)