Post Reply 
 
Thread Rating:
  • 0 Vote(s) - 0 Average
  • 1
  • 2
  • 3
  • 4
  • 5
D-12 development work lingers on
07-11-2012, 05:03 PM
Post: #1
D-12 development work lingers on
D-12 development work lingers on



ISLAMABAD - The development work at sector D-12 of the federal capital has been lingering on due to lack of interest of the concerned officials and Capital Development Authority (CDA), despite passage of seven years.

The sector was launched 22 years ago and development work was started in 2005. Moreover, the contract of the development work was given to a contractor at Rs 520 million and it was to be completed in two years but despite passage of seven years development could not be completed so far.

Sources said that due to the delay in development work estimated cost has increased to Rs 860 million instead of Rs 520 million.

The affectees have stopped spreading of services in Sector D-12/4, 1,2 on Service Road West because CDA did not have possession of land sources added.

It was learnt that 90 percent construction work on roads, 30 percent on water supply, 40 percent on sewerage and drainage has been completed. Moreover, 80 percent work on electricity while 60 percent on gas services has been completed in D-12 Sector.

The allotees of the Sector D-12 demanded of Chairman CDA Farkhand Iqbal to remove hurdles in the process of development to ensure early completion of development work.

Meanwhile, one week International Resource Person (IRP) workshop on Assessment in English Languages Teaching concluded here at Higher Education Commission (HEC).

The workshop was organised by English Language Teaching Reforms (ELTR) Phase-II of the HEC in collaboration with the US Embassy Islamabad.

Annie Polatsek and Strand Susan facilitated the training as international resource persons. Eighteen faculty members of different colleges and universities across Pakistan attended this course.

Managing Director Quality Assurance Agency HEC, Prof Dr Khawaja Azam Ali was the chief guest at the closing ceremony. Mission Director Communication US Embassy, Thomas Miller was also present at the ceremony as the guest of honour.

The main objectives of the workshop were to delineate the aspects of testing, to discuss elements of evaluation, testing and alternative assessment and evaluate ways to assess a variety of language activities and skills. The workshop was a fusion of innovative activities and theory to provide an all-out exposure of assessment and evaluation techniques to English fraternity.

This workshop on “Assessment in ELT” aimed at creating awareness of the concepts, principles and concerns of language testing and evaluation among the fraternity of English faculty of Universities and colleges. Annie Polatsek and Strand Susan explained in detail the basic concepts and theories underlying testing, evaluation and alternative assessment. Both the resource persons came forward with unique and striking ideas to enable the participants to construct tests for the assessment of linguistic competence (grammar and vocabulary) and language skills (reading, writing, speaking, and listening) and to use alternative forms of assessment in their classroom, in addition to traditional achievement tests.

Thomas Miller appreciated the role of HEC in promoting education.

He mentioned assessment was the main driver of learning process. Mr. Miller showed his satisfaction on the fact that the course participants were representing all parts of the country, especially teachers from colleges and universities of far off areas were given preference in this course. He thanked HEC on an excellent collaboration and assured that such partnership with HEC would continue in future.

Speaking on the occasion, Prof Dr Khawaja Azam Ali said that assessment was the most important area, especially in a semester system. The main difference in the annual and semester system is assessment procedure, which discourages rote learning and cramming. Innovative methodologies and practices in assessment can change the learning trends. In the end the certificates were distributed among the participants.
Visit this user's website Find all posts by this user
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  LDA Begins Development Work on Journalist Colony LRE-Azan 0 851 04-27-2023 03:25 PM
Last Post: LRE-Azan
  Development work underway in Multi Residencia & Orchards Salman 0 5,101 04-24-2015 03:12 PM
Last Post: Salman
  Development work in sectors G-13, 14 to be accelerated: Usman Salman 0 7,135 11-22-2013 05:20 PM
Last Post: Salman
  DHA City Karachi Issues Tender Notice For Development Work Salman 0 12,686 10-31-2013 02:30 PM
Last Post: Salman
  CDA asked to expedite work on ICT development projects Salman 0 8,705 09-02-2013 12:43 PM
Last Post: Salman
  Jawad Paul tells CDA to speed up development work Salman 0 10,672 08-16-2013 12:08 PM
Last Post: Salman
  CDA directed to expedite work on development projects Salman 0 9,210 08-16-2013 11:58 AM
Last Post: Salman
  Development work in Sector G-14 in full swing Salman 0 4,827 04-22-2013 01:57 PM
Last Post: Salman
  Development work in rural areas govt’s top priority: Mehtab Dehar Salman 0 5,555 08-06-2012 12:50 PM
Last Post: Salman
  Ishrat for speeding up work on Lyari Development Authority housing schemes Salman 0 6,281 07-25-2012 01:50 PM
Last Post: Salman
  Development work Started In DHa Phase 8 Lahore July 09, 2012 Salman 0 26,301 07-09-2012 07:46 PM
Last Post: Salman
  Development work underway in Landhi and Korangi Salman 0 4,861 05-28-2012 12:57 PM
Last Post: Salman
  Steps taken to expedite work on development projects Salman 0 5,088 05-04-2012 01:29 PM
Last Post: Salman
  Development work in G-14 to start within one month Salman 0 4,736 04-30-2012 12:25 PM
Last Post: Salman
  CDA fails to start development work Salman 0 4,770 04-24-2012 01:06 PM
Last Post: Salman
  Private housing schemes LDA directorate to complete development work Salman 0 4,405 03-06-2012 06:34 PM
Last Post: Salman
  Allottees dismayed over delay in Sector G-14/2-3 development work Lahore_Real_Estate 0 4,352 02-01-2012 01:15 PM
Last Post: Lahore_Real_Estate
  Lack of development work irks E-12 allottees Salman 0 4,118 01-25-2012 02:11 PM
Last Post: Salman
  Lack of development work irks E-12 allottees Lahore_Real_Estate 0 3,549 01-25-2012 11:40 AM
Last Post: Lahore_Real_Estate
  Park Enclave Housing Scheme: Senate body for timely completion of development work Salman 0 4,629 01-20-2012 12:12 PM
Last Post: Salman

Forum Jump:


User(s) browsing this thread: