76 Percent Work has been Completed on Lahore Orange Line Metro Train
11-04-2017, 12:29 PM
Post: #1
76 Percent Work has been Completed on Lahore Orange Line Metro Train
LAHORE ORANGE LINE METRI TRAIN (OLMT)

LAHORE: More than 76 per cent of civil work besides 26 per cent electrical and mechanical work on Lahore Orange Line Metro Train (OLMT) project has been completed including construction of a bridge on Lahore Ring Road where laying of track for the train in progress.

This was informed during a weekly progress review meeting on Wednesday. Lahore Commissioner Abdullah Khan Sumbal chaired the review meeting and observed that work on the project was going smoothly and progress so far had been satisfactory for which the whole team deserved credit.

National Engineering Services Pakistan (NESPAK) General Manager Salman Hafeez informed the meeting that construction projects were fast moving towards completion, with package-I from Dera Gujjaran, G.T.Road to Chouburji being 87 per cent complete and package-II from Choburji to Ali Town being 59 per cent complete. The progress on Depot near Dera Gujran was 81.5 per cent while on Stabling Yard near Ali Town was 78.5 per cent.

It was further revealed at the meeting that construction of a 185 meters long bridge on railway tracks near Parachute Colony was now in the final stage. Machinery had also been imported from China for use in case of emergencies and pulling trains to the depot.

Deputy Mayor Nazir Khan Sawati, Lahore Development Authority (LDA) Chief Engineer Asrar Saeed Khan, Punjab Mass Transit Authority Manager Operations Sayed Ozair Shah, NESPAK General Manager Haseeb Khawaja, representatives of Chinese Engineering Consultant, local contractors of the project and other senior officials of various provincial departments attended the progress review meeting.

Reference: https://www.pakistantoday.com.pk/2017/11...completed/

VISIT OUR OFFICIAL WEBSITE FOR LATEST PROPERTY NEWS AND DISCUSSION: https://www.lahorerealesate.com/ads/

Visit this user's website Find all posts by this user
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  New Metro City Lahore: Invest in Exclusivity & Prime Location  LRE-Azan 0 325 04-26-2024 06:56 PM
Last Post: LRE-Azan
  Lahore Smart City Development of the Railway Line Underpass Started Good News LRE-Azan 0 817 01-24-2023 02:53 PM
Last Post: LRE-Azan
  3 Marla Villas New Metro City Kharian BSM Developers To Book Call Lahore Real Estate LRE-Azan 0 1,276 04-20-2022 06:33 PM
Last Post: LRE-Azan
  DHA Lahore Phase 9 Prism Main Gate Work Completed | Inauguration Very Soon LRE-Azan 0 1,254 12-31-2021 06:29 PM
Last Post: LRE-Azan
  Lahore Ring Road SL-3 Work Has not Been Started Yet LRE-Azan 0 2,133 10-11-2019 02:00 PM
Last Post: LRE-Azan
  Signal Free Corridor from Walton Road to Phase 5 Completed – DHA Lahore Update LRE-Azan 0 2,396 06-22-2018 04:06 PM
Last Post: LRE-Azan
  Orange Line Metro Train Project Lahore Latest Development images LRE-Azan 0 5,571 05-12-2018 01:16 PM
Last Post: LRE-Azan
  Two more train sets for the Lahore Orange Line Metro Train Reach Lahore LRE-Azan 0 2,422 03-09-2018 12:22 PM
Last Post: LRE-Azan
  Pakistan Railways has started Cargo Express Train LRE-Azan 0 2,244 12-19-2017 05:20 PM
Last Post: LRE-Azan
  The 2 More Trains Will be Reached In Lahore Today of Orange Line Project Lahore LRE-Azan 0 2,602 11-10-2017 01:03 PM
Last Post: LRE-Azan
  Gwadar Free Economic Zone of 1st Phase will be Completed In Next Month LRE-Azan 0 2,751 11-06-2017 04:04 PM
Last Post: LRE-Azan
  Longest interchange In Lahore will be Completed soon Salman 0 2,260 10-16-2017 03:29 PM
Last Post: Salman
  Lahore Multan Motorway Will Be Completed In April 2018 Salman 0 2,474 10-09-2017 04:04 PM
Last Post: Salman
  Metro Train Engine Reached At Lahore Salman 0 2,369 10-02-2017 06:38 PM
Last Post: Salman
  12 Orange Train stations near completion Salman 0 2,647 09-28-2017 06:01 PM
Last Post: Salman
  CPEC railway line economic zone projects face delay Salman 0 2,479 09-22-2017 06:21 PM
Last Post: Salman
  Orange Line Metro Train To Be Fully Automatic Salman 0 2,413 09-13-2017 05:08 PM
Last Post: Salman
  Connection NFC 2 and main bahria 160ft road completed Salman 0 2,628 02-15-2017 07:09 PM
Last Post: Salman
  Orange Line Metro Train (Progress) Salman 0 3,027 09-08-2016 05:04 PM
Last Post: Salman
  Underground Tunnel Progress (Metro Train Project) Salman 0 3,237 09-08-2016 12:01 PM
Last Post: Salman

Forum Jump:


User(s) browsing this thread: 1 Guest(s)