Post Reply 
 
Thread Rating:
  • 0 Vote(s) - 0 Average
  • 1
  • 2
  • 3
  • 4
  • 5
83.4 MW Kurram Tangi hydropower project: Stakeholders’ attitude pushes project into d
01-17-2012, 01:50 PM
Post: #1
83.4 MW Kurram Tangi hydropower project: Stakeholders’ attitude pushes project into d
83.4 MW Kurram Tangi hydropower project: Stakeholders’ attitude pushes project into deep water

* Completion of the Rs 59.561 billion project delayed for an indefinite period

ISLAMABAD: The non-serious attitude of the stakeholders of the power sector has pushed 83.4 megawatts (MW) Kurram Tangi hydropower project with accumulated cost of Rs 59.561 billion into deep water, delaying the completion of the said mega project for an indefinite period.

The initiator of the said million-dollar hydropower project in North Waziristan, Water and Power Development Authority (WAPDA) and financial resource departments of the Federation were reluctant to clarify the reasons of the delay for commencement of the project, however WAPDA authorities linked the delay to unavailability of funds.

Interestingly, the planning wing of WAPDA had claimed the PC-1 cost of the said project up to Rs 17.205 billion and after detailed review by another major stakeholder of the Federation, the Planning Commission endorsed the document and Executive Committee of the National Economic Council (ECNEC) approved it in 2005. However, because of long delaying in the project, the actual cost of Kurram Tangi shot up to Rs 59.561 billion, showing an enormous increase of 246.18 percent, while the authority linked this huge numeric game with certain factors including worst law and order situation in the surrounding areas of the project site, some technical amendments in the dam’s infrastructure design, enhancement in storage capacity and some others.

Member of the parliamentary panel of the Senate, Senator Zahid Khan informed this scribe, that the authority has yet to settle the land acquisition issue with the residents of tribal elders of North Waziristan.

He further said that the parliamentary panel of Senate, which dealt with the water and power sector as well as the finance department, summoned WAPDA Chairman Shakeel Durani and senior officials of the Planning Commission and finance division on January 19 to probe the actual reason of delay in commencement of the said mega hydropower project.

According to sources in the Planning Commission, expenditures of WAPDA in the name of Kurram Tangi hydropower project were recorded at Rs 3.624 billion against accumulated allocation of Rs 6.14 billion in the development budget, Public Sector Development Programme (PSDP) since last six fiscal years (FY) 2006-07 to ongoing FY 2011-12.

Further details of the development budget revealed that WAPDA used Rs 50 million till end of June 2006, federal government allocated Rs 2.7 billion in PSDP 2006-07 for the said project and expenditure of the authority for Kurram Tangi hydropower project recorded the full amount of allocation for FY 2006-07, Rs 2.847 billion had been allocated for 83.4 MW hydropower project in PSDP 2007-08, while WAPDA put forward the expenditure details of Rs 874 million till end of June 2008.

Interestingly, the finance managers of the present democratic regime dropped the project from PSDP 2009-10, however the authority squandered Rs 56.300 million.

The federal government once again made allocation for WAPDA under the head of planned hydropower project in North Waziristan at Rs 576.176 million in PSDP 2010-11 and Rs 100 million for FY 2011-12, however no single penny was released for the said project.

A senior official of WAPDA, while talking to Daily Times linked the base issue of land acquisition for 83.4 MW Kurram Tangi hydropower project with availability of fund.

He said that two joint ventures including LIMAK (Turkish)-Frontier Works Organisation (FWO) and HAMBO (Korean)-Sh Abdul Razaq and Co (SARCO) Pakistan, while an individual contractor DESCON has been qualified for tendering after completion of pre-qualification phase, adding, “Tendering for construction of Kurram Tangi will be held in March 2012,” he maintained.

WAPDA claimed in respect of 83.4 MW hydropower project, feasibility study, detailed engineering design and tender documents were completed in July with an elevated height to enhance the storage capacity, while project director has been appointed under general manager (North) for construction of the project. The authority has paid Rs 17 million to District Coordination Officer (DCO) and District Officer Revenue (DOR) Banu so far for acquiring land and Khyber Pakhtunkhwa government assured full support along with all out security arrangements to ensure security of all stakeholders during construction of this mega project
Visit this user's website Find all posts by this user
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  Latest Updates on Cheel Chowk Flyover and Walton Road ADA Nala Project in Lahore LRE-Azan 0 54 11-12-2024 11:11 AM
Last Post: LRE-Azan
  CM Naqvi Leads Project Review and Inspects CBD Boulevard Developments LRE-Azan 0 1,059 01-25-2024 03:37 PM
Last Post: LRE-Azan
  CM Naqvi Drives Forward Controlled Access Corridor Band Road Project in Lahore LRE-Azan 0 1,005 01-24-2024 06:40 PM
Last Post: LRE-Azan
  Commissioner Announces Key Milestones and Schedule for Rawalpindi Ring Road Project LRE-Azan 0 1,179 01-23-2024 03:37 PM
Last Post: LRE-Azan
  PM Kakar Emphasizes Pakistan-China Collaboration for CPEC Project Completion LRE-Azan 0 625 01-23-2024 03:31 PM
Last Post: LRE-Azan
  Final Stages of Quetta Safe City Project Signal Progress in Counterterrorism and Poli LRE-Azan 0 551 01-19-2024 06:47 PM
Last Post: LRE-Azan
  CDA Unveils Blueprint for Model Village Project in Islamabad Capital Territory LRE-Azan 0 601 01-17-2024 06:13 PM
Last Post: LRE-Azan
  Latest News Lahore-Sialkot Motorway Link Road Project Set to Open in January LRE-Azan 0 665 01-16-2024 02:26 PM
Last Post: LRE-Azan
  Lahore-Sialkot Motorway Link Road Project Set to Open in January LRE-Azan 0 896 01-16-2024 02:25 PM
Last Post: LRE-Azan
  CBD Punjab Boulevard and Walton Project Advancements Revealed LRE-Azan 0 585 01-09-2024 03:27 PM
Last Post: LRE-Azan
  KDA Seeks Land Allotment Adjacent to Northern Bypass for Housing Project Launch LRE-Azan 0 634 01-02-2024 06:16 PM
Last Post: LRE-Azan
  Rawalpindi Ring Road (RRR) Project: 12% Completion, Anticipated Opening in August LRE-Azan 0 638 01-02-2024 06:14 PM
Last Post: LRE-Azan
  Signal-Free Walton Road Project: Tackling 18-Kilometer Infrastructure and Drainage Is LRE-Azan 0 590 12-11-2023 04:06 PM
Last Post: LRE-Azan
  Infrastructure Enhancement Unleashes Growth: Six Highways Project Boosts Sialkot Indu LRE-Azan 0 561 11-22-2023 01:11 PM
Last Post: LRE-Azan
  Interest from 21 Construction Firms for Margalla Avenue-M1 Link Project LRE-Azan 0 665 11-01-2023 06:02 PM
Last Post: LRE-Azan
  CDA Proposes New Dam Project to Meet Islamabad Water Demand LRE-Azan 0 602 10-13-2023 07:55 PM
Last Post: LRE-Azan
  Rawalpindi Ring Road Project Set to Be Completed in One Year LRE-Azan 0 630 10-11-2023 07:13 PM
Last Post: LRE-Azan
  Registration Process Commences for CBD Project Dealers – A Lucrative Opportunity LRE-Azan 0 629 10-04-2023 07:12 PM
Last Post: LRE-Azan
  Massive PKR 8 Billion Project Initiated to Tackle Drainage Issues on Lahore's Walton LRE-Azan 0 585 10-02-2023 03:28 PM
Last Post: LRE-Azan
  Rawalpindi Ring Road Project Faces Complication of Missing Land Record LRE-Azan 0 710 09-13-2023 07:36 PM
Last Post: LRE-Azan

Forum Jump:


User(s) browsing this thread: 1 Guest(s)