Post Reply 
 
Thread Rating:
  • 0 Vote(s) - 0 Average
  • 1
  • 2
  • 3
  • 4
  • 5
Islamabad: CDA to probe D-12 development work delay
06-22-2008, 08:57 AM
Post: #1
Islamabad: CDA to probe D-12 development work delay
ISLAMABAD: Capital Development Authority (CDA) Chairman Kamran Lashari has constituted a two-member committee to probe why the construction firm has not resumed development work in Sector D-12, sources said.

They said the firm was not complying with the authority’s directive to restart the work. The sources said the committee, comprising CDA Member Engineering Moeenuddin Kakakhel and Member Planning Raja Nosherwan, would submit its report tomorrow (Monday).

They said that development work in the sector was started on May 16, 2005 and its completion was due on November 15, 2006. They said relaxation was granted to the firm for accomplishing the plan by June 30, 2007, but to no avail.

The sources said the firm again could not make the best of one-year extension in deadline and the CDA failed in allotting possession letters to the allottees by June 30, 2008 as per its promise.

They said only 65 percent of the work had been completed, as it had been halted during the last four months. They said the project’s cost was increased on the demand of the firm, but now it was requesting for higher rates. They said the firm was neither restarting the work nor willing to quit. They said, quoting Lashari, that more delay would not be tolerated in this connection. online

http://www.dailytimes.com.pk/default.asp...008_pg11_9
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  CDA To Invite Tenders For The Development Of Sector C-16 Islamabad* LRE-Azan 0 932 04-29-2023 06:14 PM
Last Post: LRE-Azan
  LDA Begins Development Work on Journalist Colony LRE-Azan 0 854 04-27-2023 03:25 PM
Last Post: LRE-Azan
  After a protracted 7 years, CDA resumes development in Sector C-15 in Islamabad LRE-Azan 0 829 04-03-2023 06:19 PM
Last Post: LRE-Azan
  Islamabad: Work on Bhara Kahu Bypass to Start Next Month LRE-Azan 0 1,317 11-02-2021 06:34 PM
Last Post: LRE-Azan
  Development work underway in Multi Residencia & Orchards Salman 0 5,102 04-24-2015 03:12 PM
Last Post: Salman
  Development projects face delay due to rains Salman 0 6,211 03-31-2014 07:36 PM
Last Post: Salman
  NAB starts probe into FGEHF plots allotment, recruitment's Salman 0 5,288 02-25-2014 01:19 PM
Last Post: Salman
  Minister dissatisfied over delay in Kurri Road project Salman 0 5,010 02-25-2014 01:16 PM
Last Post: Salman
  EOBI Land Scam – Supreme Court Ordains To Conduct Fair Probe Salman 0 6,161 12-17-2013 01:42 PM
Last Post: Salman
  Delay in approval of building plans by CDA irks investors Salman 0 7,593 11-29-2013 01:17 PM
Last Post: Salman
  Development work in sectors G-13, 14 to be accelerated: Usman Salman 0 7,136 11-22-2013 05:20 PM
Last Post: Salman
  DHA City Karachi Issues Tender Notice For Development Work Salman 0 12,690 10-31-2013 02:30 PM
Last Post: Salman
  Delay in completion of project irks Pindiites Salman 0 7,280 09-30-2013 03:45 PM
Last Post: Salman
  CDA asked to expedite work on ICT development projects Salman 0 8,708 09-02-2013 12:43 PM
Last Post: Salman
  Jawad Paul tells CDA to speed up development work Salman 0 10,676 08-16-2013 12:08 PM
Last Post: Salman
  CDA directed to expedite work on development projects Salman 0 9,214 08-16-2013 11:58 AM
Last Post: Salman
  Delay in widening of Kashmir Highway causing traffic jams Salman 0 9,914 08-01-2013 12:45 PM
Last Post: Salman
  The EOBI Scandal Probe Reveals Corruption of Yet Another 2 Billion Salman 0 7,005 07-29-2013 12:42 PM
Last Post: Salman
  The Judicial Probe Into The EOBI Scandal Reveals Corruption Of Billions Of Rupees Salman 0 6,690 07-23-2013 01:01 PM
Last Post: Salman
  Development work in Sector G-14 in full swing Salman 0 4,828 04-22-2013 01:57 PM
Last Post: Salman

Forum Jump:


User(s) browsing this thread: 1 Guest(s)